Those damp, moldy mall entrances will finally get torn out and replaced beginning April 15, Erik Fix says.
Contracts are in place and the contractors are working on the procurement of supplies, the assistant city manager said Friday in response to The Batavian’s request for an update.
“The plan is to have everything needed on site prior to starting, so once we demo, the project can be finished in 60 to 90 days, so that we can limit the amount of time we cannot use certain entrances,” Fix said. “Some HVAC and electrical work may take place prior to the April 15th date, but that is when you will start to see the demolition taking place. The silos need to be taken apart one piece at a time, so it won’t be like a wrecking ball-type situation. There will be plenty of communication prior to the start date to ensure the public will know how to access the mall.”
The entrances at City Hall and near Dan’s Tire will remain as is, so the public will have access to them throughout the silo replacement process.
“We’re hoping to begin demolition all at once, they will take them all down and build them all backup,” he said during Monday’s City Council business meeting.
Downtown Revitalization Initiative funding of about $1 million has been set aside for the silo project, with $120,000 for the design process and the remaining money for actually redesigning the silos.