Work is progressing Monday on the Jackson Street waterline replacement project between Ellicott and Chestnut streets in the City of Batavia. Crews from Blue Heron Construction of Jordan are replacing approximately 2,250 linear feet of 4- and 6-inch water mains with 8-inch mains during the pre-winter project.
Blue Heron was the successful candidate for the job out of several bids. City Council awarded the company its bid of $1,353,000 during the city's Aug. 14 business meeting.