Hard to believe, but nearly two years have passed since the groundbreaking for the new Genesee County Jail, and officials are now talking about its completion being on time for this spring.
"I took a tour of the jail. Things look really good," Legislator Gary Maha said during this week's Public Service meeting.
Beyond aesthetics, crews have been on site ensuring that safety, infrastructure and technology have also been properly put in place since construction began in May 2022 after several years of the county's initial planning and saving for the $70 million, 184-bed facility.
Regular updates by The Pike Company Senior Project Manager Carl York have kept legislators apprised about change orders, on-site tasks, weather issues, supply chain delays, worker injuries (there have been few), and the expected timeline with each passing month.
About 100 oversized cement pods made news in January 2023 as they were slowly hauled down Route 5 to the site of the new jail at 3839 West Main Street Road, Batavia. A ceremonial beam signing took place in July 2023 as work crews continued to put the pieces together for what York has continuously labeled a financially on-target and on-schedule project.
True, there have been supply chain issues and change orders throughout the construction process, but all the while York said spending was on budget. At one point, the timeline lost seven days due to rain, but the project remained on course, he said, and that still holds true for a March 15 deadline.
Legislature Chairwoman Shelley Stein asked if there would be tours available for remaining legislators, and Deputy Highway Superintendent Paul Osborn said most likely by April. The prison is expected to be up and running in June or July.