Judge issues preliminary injunction, halting STAMP sewer line in Orleans County

By Tom Rivers
sewer pipeline stamp
Traffic was limited to one-way on Route 63 on Aug. 30 while contractors installed a new sewer pipe in the Town of Alabama.
Photo by Tom Rivers.

A State Supreme Court has issued a preliminary injunction and temporarily won’t be allowing a sewer line to be constructed in Orleans County, running from the STAMP manufacturing site about 10 miles north to Oak Orchard Creek.

Contractors started installing the 20-inch sewer main last month and are headed north along 63. They haven’t reached Orleans County yet.

Judge Sanford Church on Monday issued the preliminary injunction and set a court date for Oct. 23 at the County Courthouse in Albion.

Orleans County has filed a lawsuit against Genesee County Industrial Development Agency of Batavia, Genesee Gateway Local Development Corporation of Batavia, Stamp Sewer Works, Inc. of Batavia, G. Devincentis & Son Construction Co., Inc. of Binghamton, Clark Patterson Lee of Rochester, and Highlander Construction of Memphis, NY.

Orleans contends the GCEDC didn’t properly form STAMP Sewer Works for the project and doesn’t have a right to seek construction easements in Orleans, which is outside Genesee County. Genesee never asked for Orleans permission to undertake the project, Orleans says in the suit.

Orleans economic development officials are also concerned the discharge of treated water from STAMP, at up to 6 million gallons a day at full capacity, could limit economic development efforts in Medina by overtaxing the creek.

GCEDC notes engineering reports say there would be another 10 million gallons of daily capacity for the creek from the Medina sewer plant if STAMP were at full capacity. The first two tenants at STAMP, Plug Power and Edwards Vacuum, would have a daily discharge of 50,000 gallons of treated wastewater GCEDC said.

GCEDC says it secured all required permits and approvals for construction and use of the force main for the sewer, including a right-of-way permit from the United States Fish and Wildlife Service to cross the Iroquois National Wildlife Refuge and a discharge permit from the New York State Department of Environmental Conservation.

The Iroquois National Wildlife Refuge has temporarily paused drilling as part of the construction after sinkholes were observed in the right of way of the refuge.

There also are fluids associated with subsurface drilling that appeared on the refuge surface outside the perimeter of the right of way, the U.S. Fish and Wildlife Service said in a statement on Tuesday.

Craig Leslie, GCEDC attorney, said in a Sept. 11 court filing, asked the judge not to approve a preliminary injunction and temporary restraining order.

“Orleans County’s allegations are wholly inconsistent with the facts and the law and smack of a frivolous and politicized attack on the STAMP project,” wrote Leslie, an attorney with Phillips Lytle LLP.

Orleans County, represented by attorney Jennifer Persico of Lippes Mathias LLP, contends the Genesee agencies and others named and in the lawsuit “have been engaged in a conspiracy not only to violate General Municipal and Transportation Corporations Law but also to defraud the residents of Orleans County and citizens of New York State in general by misusing millions of taxpayer dollars to fund an unauthorized project all while acting outside of their respective authority,” according to the Orleans court filing on Sept. 11, seeking the preliminary injunction.

Photo and story courtesy OrleansHub. Tom Rivers is editor of OrleansHub.

GCEDC board chair releases open letter to community in response to Orleans County lawsuit

By Howard B. Owens

See also: Orleans County files suit over WNY STAMP sewer line

Press release:

A number of concerns have been raised about the impacts of the construction of an underground pipeline that would discharge treated water from businesses at STAMP into Oak Orchard Creek.

These are concerns that we have taken very seriously and addressed.  Multiple engineering studies and peer engineering and environmental regulatory reviews have been conducted to assess potential impacts of discharging this treated water into the Creek.  This process is similar to how municipalities treat water before it is discharged into local waterways.

While existing businesses at STAMP, including Plug Power and Edwards, would discharge approximately 50,000 gallons per day of treated water into Oak Orchard Creek, the studies and peer reviews assessed the impacts of the potential for a maximum of 6 million gallons per day as if STAMP was at full build-out.

The various studies and peer reviews conducted by engineering professionals took that maximum level into account and determined that the increased flow from the STAMP discharge will not have a noticeable impact on the 100-year flood elevations downstream, nor will it impact stream velocity, water levels, water quality impairments and/or area-wide erosion.

Concerns also have been raised about potentially impacting the capacity at water treatment facilities in neighboring communities, which could negatively impact bringing new businesses and/or assist business expansion because of a lack of capacity.

Again, citing these same studies and peer reviews for the potential for a maximum of 6 million gallons per day if STAMP was at full build-out, it was determined that:

  • The increase in surface water elevations in Oak Orchard Creek during a 10-year storm event would be approximately 1/8” to 1/4”, with STAMP discharging at the maximum expected level of 6 MGD. 
  • Given the above, the Medina water treatment plant, which currently operates with a maximum permitted level of treating 4.5 MGD, could expand by another 10 MGD in order to accommodate new capacity for business growth and/or expansion without impact from STAMP’s maximum expected 6 MGD discharge.  
  • An adjoining dam to Oak Orchard Creek could absorb the 6 MGD into its storage capacity without modification to the dam’s operations.  

We want to support our partners in economic development to assist any we can to enhance investment in the GLOW region.  We would not advocate for something that would be detrimental to our partners, as we all are working collaboratively to bring prosperity to our region.

Finally, we want to thank the approximately 38 landowners who agreed to temporary and permanent easements on their properties to allow the underground pipeline to be constructed.  We appreciate their understanding of the temporary and permanent need to use their properties for this critically important regional economic development initiative.

Please visit www.informationaboutstamp.com to review the various engineering studies and peer-reviewed documents related to this project.

Sincerely,

Peter Zeliff
Chairman
Genesee County Economic Development Center

Orleans County files suit over WNY STAMP sewer line

By Tom Rivers
stamp sewer line
The new sewer line is shown on Aug. 12 on Route 63 in the Town of Alabama, Genesee County. Orleans County officials are seeking to stop the construction from going to the STAMP site about 10 miles north to the Oak Orchard Creek.
Photo by Tom Rivers/OrleansHub

Story courtesy OrleansHub.com

Orleans County is suing its neighbor to try to stop a sewer line from coming into the Town of Shelby and depositing up to 6 million gallons of what Orleans says is “contaminated” water into the Oak Orchard Creek.

The county on Monday filed an Article 78 complaint in State Supreme Court, seeking to halt placement of a sewer line from the STAMP site to the Oak Orchard Creek, a 9.5-mile long pipe along Route 63 that has been under construction since Aug. 3.

Orleans is asking for a temporary restraining order to stop construction so the arguments can be heard in court without the pipeline getting built in Orleans County.


See also: GCEDC board chair releases open letter to community in response to Orleans County lawsuit


The court action from Orleans County is called a “frivolous and politicized attack” in a court response from Craig A. Leslie, attorney for GCEDC and others named in the suit.

Orleans County officials contend the county never gave its permission for the project, and the Genesee County Economic Development Center formed a “sham corporation” – STAMP Sewer Works – to make the project happen.

The STAMP site is 1,250 acres and is considered a top priority for economic development officials in the region. It is targeted for advanced manufacturing – semiconductors and renewables manufacturing.

Plug Power is currently building a $290 million facility at STAMP for a green hydrogen production facility that includes an electric substation. The new facility will produce 45 metric tons of green liquid hydrogen daily when fully operational, making it the largest green hydrogen production facility in North America. Plug will employ 60 people.

Another company, Edwards Vacuum, announced last November it would build a $319 million “factory of the future” at STAMP in a project serving the semiconductor industry. Edwards plans to employ 600 high-skill professionals at the semiconductor dry pump manufacturing facility.

The commitments from the two companies follow a 20-year effort to develop STAMP in a rural area of Genesee County, only a few miles south of the Orleans County border. STAMP has been pushed by U.S. Senate Majority Leader Charles Schumer, Gov. Kathy Hochul and her predecessor, Andrew Cuomo.

But Orleans County officials say the Genesee County Economic Development Center has been driving the contracts for the project, including engineering and construction – and that is illegal because an economic development agency can’t fund and push projects outside its own county unless it has permission from the other municipalities, Jennifer Persico, an attorney representing Orleans County, wrote in the complaint filed in State Supreme Court in Orleans County.

orleans attorney
Jennifer Persico, an attorney with Lippes Mathias LLP, speaks during an eminent domain public hearing on July 27. She said at the hearing that the Genesee County Economic Development Center illegally created STAMP Sewer Works as “a sham corporation” to do the eminent domain proceedings against two Orleans County property owners.
Photo by Tom Rivers/OreleansHub

In the court filing, she said Orleans “strenuously objects” to the sewer project.

Genesee County EDC is illegally funding a project outside its jurisdiction, Orleans contends in its complaint. The EDC paid for easements to allow for temporary construction, including all but two in Shelby. Orleans County secured two easements in Shelby with the stipulation no sewer line can be constructed.

Orleans officials contend the sewer discharge could limit the county’s efforts to develop its own business park in Medina, and the water may cause flooding and hurt the county’s $30 million annual fishing industry at the Oak Orchard, which is world renowned for salmon and trout fishing.

GCEDC, on March 25, 2021, awarded a $9,777,000 contract to G. DeVincentis & Son Construction Company for the 20-inch sewer main, which goes from the northern refuge boundary to the north of Shelby Center. GCEDC accepted a low bid from Highlander for construction at $5,193,445 and approved a $900,000 contract and a $560,000 contract to Clark Patterson Lee for engineering services for the sewer project. GCEDC approved the bids without the consent of Orleans County.

The request for bids shows GCEDC contemplated construction in Orleans County without the consent of Orleans, Persico said.

GCEDC also has purchased 18 temporary easements in Orleans County to allow for construction of the sewer line, without consent of Orleans, a violation of general municipal law, according to the complaint.

Orleans, in the complaint, also faults Genesee County EDC for improperly forming STAMP Sewer Works, for illegally funding and noticing the eminent domain hearing at the Alabama fire hall on July 27.

Orleans seeks to have the Supreme Court annul the easements. The county also seeks to stop the GCEDC-backed project in Orleans without the county support. That includes efforts from the GCEDC-affiliated Genesee Gateway Local Development Corporation and STAMP Sewer Works.

Leslie, attorney for GCEDC, asked the judge, Frank Caruso, not to approve a temporary restraining order on the project. Leslie said the sewer line construction has received all of the needed environmental and right-of-way permits from the state Department of Transportation and the U.S. Fish and Wildlife Service to cross the Iroquois National Wildlife Refuge.

Leslie said Orleans County shouldn’t be granted a temporary restraining order because the project is still weeks and even months from getting into Orleans. Persico wrote in her court filing the project was likely a matter of hours or days until it started in Orleans. The contractor is currently installing the sewer line in the refuge in Genesee County, Leslie wrote.

Orleans is beyond its authority and is seeking to stop all sewer line construction when the project is currently solely in Genesee County.

Leslie, the GCEDC attorney, said the claim that GCEDC is using its own money is false because the funding is part of $33 million awarded for STAMP development by Empire State Development, a state entity “which fully supports the STAMP project,” Leslie wrote.

He responded that the Town of Shelby gave its consent to the sewer line project, and so did the Orleans County Department of Health.

He asked the judge to deny the Orleans request for a preliminary injunction and temporary restraining order.

“Orleans County will sustain no injury by the continued construction of the Force Main, particularly in Genesee County, while this matter is appropriately determined by this Court,” Leslie wrote to Judge Caruso. “Meanwhile, STAMP Sewer will be irreparably harmed if the overbroad and unreasonable order requested by Orleans County is granted.”

PUBLISHER'S NOTE: The Batavian sought additional comment from GCEDC, and a spokesman referred us to a website that has been set up to address the issues raised by the lawsuit

Plug Power awarded low-cost Niagara hydropower allocation by NY Power Authority

By Press Release

Press release:

Governor Kathy Hochul today announced that the New York Power Authority Board of Trustees approved economic development awards to three firms that will spur more than $508 million in capital investments and create 205 jobs. 

Included among the approved items are low-cost hydropower allocations to Plug Power, a New York-headquartered hydrogen fuel cell manufacturer, for further development of its Genesee County site. 

The NYPA board also approved low-cost hydropower allocations to facilitate an expansion in Niagara Falls for EnerPlate, an electroplating service provider for grid-scale battery systems, and CWT, a hatching eggs producer for the global poultry industry, expanding in Watertown. 

"New York's growing clean energy infrastructure and local economic development go hand in hand," Governor Hochul said. "The items approved today by the NYPA Board of Trustees will create good-paying jobs and spark hundreds of millions of dollars of investment in communities in Western and Northern New York." 

At today's meeting, the NYPA board approved a 50-megawatt (MW) low-cost Niagara hydropower allocation to Plug Power, located at the Genesee County's Science, Technology & Advanced Manufacturing Park (STAMP), to support the firm's $387 million green hydrogen fuel production expansion project that will lead to the creation of 19 additional jobs at the location. The firm is underway with its construction of the $290 million green hydrogen fuel production facility at the site that was announced by Governor Hochul in 2021. The expansion project will increase the capacity of the planned hydrogen production from an estimated 45 tons per day to 74 tons per day. The NYPA board also approved an additional 62 MW of High Load Factor power that NYPA will procure for Plug Power on the energy market.

The Power Authority supports Plug Power at three other locations: Slingerlands, which completed construction in January, Latham, and West Henrietta. In total, NYPA supports Plug Power with 272 MW of low-cost power, supporting more than 2,100 jobs throughout the state.

GCEDC board approves financial agreements with Edwards Vacuum at STAMP

By Press Release

Press release:

The Genesee County Economic Development Center (GCEDC) Board approved financial agreements to support Edwards Vacuum, part of the Atlas Copco Group, for the first phase of the company’s $209 million semiconductor dry pump manufacturing facility at the Science Technology and Advanced Manufacturing Park (STAMP) in the town of Alabama, NY at its February 2, 2023 meeting. 

Edwards Vacuum’s “factory of the future” will serve the semiconductor industry and advanced manufacturing sectors and create approximately 343 new high-paying jobs. The facility is projected to generate more than $13.4 million in future revenues to the Town of Alabama, Genesee County, Oakfield-Alabama School District, and the Alabama Fire Department over 20 years.

Atlas Copco USA Holdings Inc. & Subsidiaries (Edwards Vacuum) has requested sales tax exemptions of approximately $4.34 million and a 20-year property tax abatement of approximately $12.85 million. The project is estimated to generate $644 million in payroll and projected future municipal revenues, and a $39 benefit to the local economy for every $1 of public investment.

Hawley applauds major semiconductor investment by Edwards Vacuum in Genesee County

By Press Release

Press release:

Assemblyman Steve Hawley (R, C - Batavia) today praised the recent announcement that Edwards Vacuum, a British-based world leader in vacuum and abatement equipment in the semiconductor industry and part of the Atlas Copco Group, has chosen the Western New York Science & Technology Advanced Manufacturing Park (STAMP)  in 139th A.D. as the location for its new $319 million, U.S. dry pump manufacturing facility. The specific technology that will be produced at the new facility is an integral part of the sensitive manufacturing process.

This highly-protected technology and process will make the new facility one of a few globally that will have the ability to produce this product. Hawley noted that this serious investment will attract some of the best minds and leaders in the semiconductor field across the world to relocate and grow in Western New York.

“New York continues to be a serious global player in the semiconductor world, and for our community to be home to this future facility reinforces the meaningful commitment we all have to bring jobs to our area and grow our economy,” said Hawley. “The trickle-down positive impact this will have on the district, for economic growth, our schools and future success, cannot be underscored. Creating 600 jobs is significant and I could not be prouder to have those jobs located in our region.”

With the recent global supply chain issues that have caused shortages in product and increases in prices for everything from cars to cell phones, Hawley believes this will better position New Yorkers and Americans across the country to economically benefit from this investment.

“This is welcome news not only for the significant local economic impact, but this will help everyday New Yorkers and Americans to better afford the wide array of consumer goods tied to the semiconductor technology. It’s an extremely exciting day for our region and I look forward to future growth,” concluded Hawley.

There's still a lot of work to do before construction starts on new Edwards Vacuum plant at STAMP

By Howard B. Owens

The commitment is in place but there is still a lot of work to be done before construction can begin on the new manufacturing facility Edwards Vacuum plans to build at WNY STAMP.

Steve Hyde, CEO of GCEDC, said the proposed project, once built out, with 600 jobs, will be the largest new manufacturing plant in Genesee County history.

"That's about a 20 percent increase in our manufacturing employment," Hyde said.

But before the first person can be hired, there are permits to be obtained, an environmental review process to complete, site plans to review, and an incentive package with GCEDC to negotiate.

The permitting process will make the coming months a bit busier for officials in the Town of Alabama.

Typically, job-creation projects receive three primary tax breaks. The first is a PILOT, or payment in lieu of taxes. The PILOT forgives a portion of property taxes (the portion derived from an increase in assessed value) in exchange for payments to local governments.  The second is a sales tax abatement on construction materials. And the third is a mortgage tax abatement. 

GCEDC has yet to reach an agreement with Edwards on those incentives, which will require a public hearing and board approval once the details are worked out.

"All of that comes down to a fundamental thing -- is it a competitive world or not?" Hyde said. "And it's a very competitive world, especially for projects in the semiconductor industry. So you know, those are all important pieces that are negotiated."

Edwards doesn't hold all the cards in any negotiation, however.  In prior interviews, both Hyde and Sen. Charles Schumer pointed out that STAMP is located along a growing semiconductor corridor between Fishkill and Ohio, and the Micron Technologies plant announced last month for the Syracuse area is a significant large potential customer for Edwards.  And a source in Gov. Kathy Hochul's office pointed out in an email today Wolfspeed and Global Foundries, among others along the I-90 corridor, are existing or potential customers for Edwards.

STAMP also benefits from a renewable energy source, Niagara Falls.

Edwards Vacuum also stands to benefit from $20 million in incentives from the State of New York.  Most of that money comes in the form of Excelsior Jobs Tax Credits.  The company only receives the tax credits if they make the qualifying hires.

There is also a workforce development grant that Edwards can earn as it builds out its staff.

The increase in new plant development across the nation is being driven largely by the CHIPS and Science Act, a bill authored by Schumer, that provides $59 billion in grants along with tax credits for companies building out the nation's capacity for producing computer chips.

Edwards is moving forward with its plans even though the company cannot yet apply for CHIPS assistance.

"(Edwards) has plans to put in their own version of a CHIPS application," Hyde said. "But no one has an official commitment yet because the window isn't even open to put the applications in. The Department of Commerce says, I think, it's February when they'll start taking applications. And I know these guys plan on putting in a very thoughtful application as well."

If all goes to plan -- and Hyde said the GCEDC staff is committed to getting through the process smoothly -- contractors for Edwards could put the first shovel into the ground in the spring.

Edwards has committed to an 80-acre parcel in the northeast quadrant of STAMP, all east of Crosby Road.

One additional job for GCEDC is building out the infrastructure, such as sewer and water, for the site.  Hyde said GCEDC will apply for a new state grant program to help pay for building infrastructure.

Edwards is planning to invest $319 million to build a manufacturing plant in two phases. The first phase will be 255,000 square feet, with 240,000 square feet dedicated to manufacturing. The remaining floor space will be used for a warehouse and administration.  The second phase will be 130,000 square feet.  

The company hopes to complete the first phase by the fourth quarter of 2024 and in that first phase, will employ from 300 to 350 people.  The second phase will round out the anticipated 600 new hires sometime in 2026.

"They're not letting any grass grow under their feet on this project," Hyde said.

Photo: File photo.

Schumer: Edwards Vacuum coming to STAMP will entice more semiconductor companies to locate here

By Howard B. Owens

This morning's announcement that Edwards Vacuum is going to build a $319 million dry-pump manufacturing facility at WNY STAMP is a good indication, said Sen. Charles Schumer, that there are more high-tech companies who will choose to locate new plants at the park.

"We had a good chance before landing Edwards and now those chances are even better," Schumer told The Batavian during an exclusive interview.

Edwards is a major player in the semiconductor industry, Schumer said, and the decision by the company's CEO, Geert Follens, helps validate STAMP as a viable option for other companies in the semiconductor supply chain as well as a semiconductor fabricator.

The British-based company makes the vacuums that help keep chip manufacturing clean rooms clean.

"Once you land a serious company like this, other semiconductor companies are going to take notice," Schumer said.

Schumer is the author of the CHIPs and Science Act, which provides $52 billion in manufacturing grants and establishes a 25 percent investment tax credit for increasing semiconductor manufacturing in the U.S. 

That bill, Schumer said, was a significant factor in the decision by Micron Technologies to build a major chip manufacturing plant near Syracuse and Micron's selection of New York helped STAMP beat out a competing site in another nearby state for the Edwards facility, Schumer said. 

Phase One of Edwards Vacuum’s 240,000 square-foot campus includes manufacturing, warehouse and administration.  The company is expected to employ 600 people and the state and federal financial incentives tied to the deal require Edwards to meet that employment goal.

Edwards will also negotiate a PILOT agreement (a reduction in property taxes on the increased value of the property in exchange for payments to local governments), along with sales tax, and mortgage tax abatements with GCEDC.

In an interview with The Batavian yesterday, GCEDC Steve Hyde said there was a major announcement coming soon (which came a lot sooner than he suggested) about STAMP, and he also said there are about 20 companies with some interest in STAMP and another five or six with serious interest.

Schumer agreed with that assessment.

"There is a lot of interest in STAMP," said Schumer, a big baseball fan. "We have to land them but we're on third base and getting ready to score."

File photo of Sen. Charles Schumer at WNY STAMP in August 2020 calling for passage of the CHIPS Act. Photo by Howard Owens.

Semiconductor supply-chain business to build $319 million facility at STAMP

By Press Release

Press release:

Governor Hochul and U.S. Senate Majority Leader Charles Schumer today announced that Edwards Vacuum, a British-based world leader in vacuum and abatement equipment in the semiconductor industry and part of the Atlas Copco Group, has chosen the Western New York Science & Technology Advanced Manufacturing Park (STAMP), located in Genesee County, as the location for their new $319 million, U.S. dry pump manufacturing facility. The dry pump technology that will be produced at the new facility is a vital component to controlling the highly sensitive environment of semiconductor manufacturing processes. Phase One of Edwards Vacuum’s 240,000 square-foot campus include manufacturing, warehouse and administration. This new commitment from a global leader in the semiconductor manufacturing supply chain to invest in New York State builds on the announcement that Micron is investing an unprecedented $100 billion in Central New York.   

“This major investment from Edwards Vacuum builds on our momentum to secure New York as a leader in semiconductor manufacturing,” Governor Hochul said. “On the heels of Micron’s $100 billion commitment to Central New York, as well as New York’s Green CHIPS legislation and the federal CHIPS and Science Act, we are better positioned than ever to make New York a global hub for advanced manufacturing and attract the jobs of the future. I am thrilled to welcome Edwards Vacuum to Genesee County and look forward to working with them, as well as our local, state, and federal partners, as they make New York their home.”

The CHIPS And Science Act delivers for Upstate New York again,” said Senate Majority Leader Charles Schumer.  “I am thrilled to announce Edwards Vacuum, a major player in semiconductor supply chain, will soon power Genesee County with an over $300 million plant and 600 good-paying jobs!  From Micron’s major investment in Central NY and Wolfspeed’s new fab in Marcy, to onsemi soon beginning in the Hudson Valley and GlobalFoundries building a new fab in the Capital Region, and now Edward’s supercharging our semiconductor supply chain at Western New York’s STAMP site, Upstate is becoming the global hub for the chip industry. I told Edwards Vacuum’s top brass last month there was no better site than STAMP to locate a new plant and I’m glad they heeded my call.  With my CHIPS and Science Act as the lighting rod, we are now seeing energy flow into Upstate’s manufacturing sector like never before, and this investment will further cement that the future of microchips will be built with American-made products, crafted by New York workers.”

Kate Wilson, President of Edwards’ Semiconductor business, said, “I am delighted that we are announcing this new facility in the state of New York. Against a backdrop of growing demand, clearly showing a greater need for investment in manufacturing capabilities that are located close to our customers, we continue to commit significant investment in our operational footprint. This is critical to ensure we retain our position as the vacuum and abatement partner of choice to the global semiconductor industry.”  

Edwards Vacuum will provide internal training and education, allowing every employee to explore and advance their career opportunities. Additionally, Edwards is committed to recruiting entry-level employees from disadvantaged communities and partnering with existing community-based recruitment and training programs, to provide both soft skills and technical skills that will provide employment opportunities that have not been available in those communities previously. 

STAMP is a 1,250-acre mega site at the forefront of green manufacturing growth in New York. Developed to provide high-capacity, low-cost renewable electricity in a strategic location in the Buffalo-Rochester Tech Corridor, STAMP has attracted over $500 million of investment  by innovative companies. With over 500 available buildable acres on-site, 1.1 million people within 30 miles, and 30,000 annually enrolled engineering students at nearby colleges and universities, STAMP is positioned to accelerate New York’s growing semiconductor manufacturing, advanced manufacturing, and renewables manufacturing industries. 

Empire State Development President, CEO and Commissioner Hope Knight said, “Attracting supply chain partners in the semiconductor industry is key building a stronger ecosystem in New York State. Edwards Vacuum’s choice of STAMP for its new facility further cements New York State as a leader in the semiconductor industry.” 

New York Power Authority Interim President and CEO Justin E. Driscoll said, “Edwards Vacuum’s STAMP investment is a testament to New York’s emergence as a global leader in semiconductor manufacturing. Securing reliable supply chain partners is critical to the semiconductor industry, and projects like this showcase the unique attributes of New York that will help the industry grow here.” 

As part of the agreement with Edwards Vacuum, ESD has offered up to $21 million in a combination of performance-based Excelsior Jobs Tax Credits, Investment Tax Credits and an additional $1 million to support Workforce Development and the training of a Diverse and Inclusive Workforce in exchange for 600 new full-time jobs at the location  Additionally, the New York Power Authority Board of Trustees will review an application for low-cost Niagara hydropower at a future public meeting. 

Edwards Vacuum is anticipated to apply for agreements at a later date with the Genesee County Economic Development Center to support the company's investment at STAMP through property, sales, and mortgage tax assistance. The request would support the largest workforce and capital investment proposed by any company at a GCEDC-developed site. 

Last month, Senator Schumer personally called Edwards Vacuum President, Geert Follens, to urge the global semiconductor supply chain company to expand in Upstate New York. Senator Schumer's bipartisan CHIPS and Science Act, creates an Investment Tax Credit for semiconductor manufacturing facilities and supply chain partners such as Edwards Vacuum as well as a first of its kind $52 billion in federal incentives to spur American semiconductor research, development, manufacturing, and workforce training to bring good-paying jobs back from overseas, strengthen national security, and reestablish America's technological leadership. The bill requires recipients of these incentives to make significant worker and community investments that support equitable economic growth. Edwards Vacuum is expected to also apply for incentives under the CHIPS and Science Act.  Schumer has long supported STAMP’s development and to attract new semiconductor and advanced manufacturing companies to locate at STAMP.  Schumer said these new federal and state investments are creating a new ‘Erie Canal’ across upstate New York by attracting thousands of new jobs in the semiconductor industry from the Hudson Valley to Western New York’s STAMP. 

Semiconductors, and their supply chain partners, are vital to the nation's economic strength, serving as the brains of modern electronics, and enabling technologies critical to U.S. economic growth, national security, and global competitiveness. The industry directly employs over 277,000 people in the U.S. and supports more than 1.8 million additional domestic jobs. Semiconductors are a top five U.S. export, and the industry is the number one contributor to labor productivity, supporting improvements to the effectiveness and efficiency of virtually every economic sector — from farming to manufacturing. Earlier this year, Governor Hochul signed New York's nation-leading Green CHIPS legislation into law to attract top semiconductor manufacturing businesses to the state and secure commitments to good-paying jobs, sustainability, and community benefits.

Supply chain issues and a decline in the United States' share of global chip production are causing undue hardships to every aspect of the economy. This erosion of U.S. chip production capacity puts the nation at a strategic disadvantage in several critical areas, including national security, technological innovation, and economic growth and independence. Because more than 300 industries use chips — from cars to cellphones — their scarcity drives up prices of other consumer goods. Edwards Vacuum’s new facility will position New York State as a national leader in reshoring vital semiconductor jobs to the U.S. 

Genesee County Legislature Chair Shelley Stein said, “We are so proud that STAMP will be the location of the largest economic development investment in the history of Genesee County. On behalf of my colleagues in the Genesee County Legislature we welcome Edwards Vacuum to our community and look forward to their success here and the career opportunities they will provide for our hard-working residents. This announcement demonstrates the diligent focus of Genesee County to plan, prepare and welcome 21st-century manufacturing to our county.” 

Town of Alabama Supervisor Rob Crossen said,  “Our shared vision through the development of STAMP is to play a role in bringing new jobs and investments to Genesee County and to improve the quality of life for our residents. The latter has begun through enhanced infrastructure improvements, especially as it pertains to water services, and we’re pleased that STAMP and our community is attracting advanced manufacturing companies and good paying jobs.” 

Finger Lakes Regional Economic Development Council Co-Chairs, Greater Rochester Chamber of Commerce President and CEO Bob Duffy and SUNY Geneseo President Denise Battles said, "We congratulate Edwards Vacuum on this incredible project, and welcome them to the state-of-the-art Western NY Science, Technology and Advanced Manufacturing Park in Genesee County. These top-quality jobs will help to energize the regional economy, furthering its reputation as the center of technology and progress.

Steve Hyde, Genesee County Economic Development Center President & CEO, said, “There is a saying that economic development is a marathon and not a sprint and that has been our approach to STAMP ever since it was a concept on paper over a decade ago. That’s why it is so gratifying to see how that steady and purposeful approach is resulting in a significant return on the investment that has been made through the years by our public and private sector partners and in particular by Senator Schumer and Governor Hochul by this announcement today. This announcement shows that STAMP and our region are the ideal location for semiconductor industry growth.” 

Greater Rochester Enterprise President and CEO Matt Hurlbutt said, “Edwards Vacuum, an innovative vacuum equipment manufacturer that serves the semiconductor industry, is expanding at the Western New York Science and Technology Advanced Manufacturing Park in the Greater Rochester, NY region to capitalize on this mega site’s unique infrastructure, which includes reliable, low-cost hydropower and unlimited water supply. Rochester, NY is also attractive because of the concentration of highly skilled talent with mechanical and electrical engineering expertise and regional workforce development partners who offer stackable credential programs and certificate programs to train Edward Vacuum’s future workforce. GRE connected Edwards Vacuum to numerous economic development resources to support this expansion in Rochester and will continue to support the company as this project unfolds.” 

This major investment adds to New York's already robust semiconductor industry. In addition to Micron’s major $100 billion investment in Central New York, New York has multiple global industry chip leaders like GlobalFoundries, Wolfspeed, onsemi, and IBM. New York is also home to the world-renowned Albany Nanotech Complex, which is a multibillion-dollar public-private partnership, comprising the most advanced, publicly owned, 300-millimeter semiconductor research and development facility and bringing together premier universities and leading industry players to drive cutting-edge chip development. Because of the tireless advocacy of Governor Hochul and Senator Schumer, semiconductor supply chain companies like Edwards are also growing as well. Earlier this year Corning Incorporated invested $139 million, creating over 270 new jobs in Monroe County to meet the demands of the growing semiconductor market.

About Edwards Vacuum  
Edwards is the leading developer and manufacturer of sophisticated vacuum products, exhaust management systems and related value-added services. These are integral to manufacturing processes for semiconductors, flat panel displays, LEDs and solar cells; are used within an increasingly diverse range of industrial processes including power, glass and other coating applications, steel and other metallurgy, pharmaceutical and chemical; and for both scientific instruments and a wide range of R&D applications. 

Edwards has more than 8,000 employees worldwide engaged in the design, manufacture and support of high technology vacuum and exhaust management equipment and has state-of-the-art manufacturing facilities in Europe, Asia and North America. 

Edwards is part of the Atlas Copco Group (NASDAQ OMX Stockholm: ATCO A, ATCO B), a Sweden-based provider of industrial productivity solutions. 

Further information about Edwards can be found at www.edwardsvacuum.com 

Interest high in STAMP, Hyde says, with new project announcement possible this month

By Howard B. Owens

With a bit of luck or an answered prayer, there could be an announcement about a new tenant at STAMP in Alabama within the next 30 days, said Steve Hyde, CEO of GCEDC, in an exclusive interview with The Batavian on Monday.

"You know what, we're praying hard that the next one connects, and we've had some real big strides of late, so I'm hoping there'll be something to talk about inside of 30 days," Hyde said.

The suggestion that a deal with some sort of hi-tech firm to build a plant at the WNY Science & Technology Advanced Manufacturing Park came at the end of an interview where Hyde discussed the interest the park is drawing from semi-conductor companies, the supply chain for those companies, and renewable energy companies.

"Things are moving, the site's market-relevant now," Hyde said. "We're seeing a lot of interest."

The biggest game changer for marketing STAMP, Hyde said, is the CHIPS and Science Act.

The legislation, authored by Sen. Charles Schumer, is intended to increase the production of semiconductors -- computer chips -- in the United States and reduce the reliance in the U.S. on Chinese semiconductors.  It's seen by supporters as a national security issue.

The act provides $52 billion in manufacturing grants and establishes a 25 percent investment tax credit for increasing semiconductor manufacturing in the U.S. 

"It is critical, in my view, having lived in this industry for a decade or more, that we really need to do all we can to bring it back," Hyde said. "I applaud Sen. Schumer and a lot of our leaders. That was a bipartisan effort around CHIPS to really make this happen and now we're seeing deals from it."

One of the biggest deals so far, announced last month, is the decision by Micron Technologies to invest $100 billion to build a new plant on 1,300 acres near Syracuse

Far from losing out on that deal, the staff at GCEDC has been busy negotiating with a bevy of companies -- as many as 20 -- about space availability at Genesee County's own 1,200-acre advanced technology campus.  Hyde said there are at least five companies, and perhaps seven, that have at least a 70 percent chance of signing a deal for a facility at STAMP.

"There's a real active sales funnel at STAMP, actually," Hyde said. "It's deeper and wider than I've seen, ever."

Combined, the companies kicking tires represent $40 billion in investments and about 20,000 jobs.

Of course, they won't all fit on the campus, and depending on who eventually signs, we could see anywhere from three to six companies with facilities in the park.

The competitive landscape has shifted since STAMP was first conceived, Hyde said.  He's no longer expecting one major semiconductor company to come in and swoop up all that remains of the STAMP campus.  The project was conceived during a time when semiconductor companies only wanted to locate two or three fabrication operations in a single location, preferring to spread out manufacturing nationally, if not globally.

But as China has grown more competitive, and with the incentives of the CHIPS Act, the major firms are looking for locations that can support six to eight fabrication plants, Hyde said.  STAMP isn't designed to provide the infrastructure necessary to support that size of an operation.

He congratulated the leaders in Onondaga County for being able to put together a plan that will meet Micron's needs.

Ultimately, Micron's presence in Central New York will benefit Genesee County, he said.  It helps create a corridor of semiconductor companies and supply chain companies from Fishkill to Columbus, Ohio, including projects in Utica and Albany, with STAMP just off the I-90 that helps tie it all together.

"Honestly, a lot of these supply chain and semiconductor players like to be nearby for transportation logistics, but they don't necessarily want to be right in the back yard of another firm because of workforce (availability)."

A smaller semiconductor manufacturer might take an interest in STAMP, but Hyde suggested it's more likely that supply chain companies will move in the firms that supply semiconductor manufacturers with their tools and technological support.

"It could become a hub for semiconductor players that maybe don't take the whole campus, but fit in nicely, and it almost becomes like a hub for the semiconductor industry," Hyde said. "We've got some real interest in that, in that space right now." 

There remains high interest among green energy companies because of the renewable power source available at STAMP (Niagara Falls). It helps that Plug Power is already building what will be the nation's largest green hydrogen plant, Hyde said.

There's also a developer from Indiana who is interested in acquiring the southern portion of the STAMP site, and that developer would do some advance builds in order to attract prospective clients.

"They've got a marquee list of vendors," Hyde said.

Hyde is never one to give too much away about the deals the team at GCEDC is working on, but he didn't hide his optimism that good things are coming soon for STAMP.

"It's pretty cool that a dozen years ago, when we really kind of defined the hope and strategy and vision for the site, that those sectors that were the focus then are the hot ones now, with federal incentives really helping drive that interest level like never before," Hyde said.

Photo: File photo of Steve Hyde from 2015 by Howard Owens.

Schumer: 'We want to build the future in Batavia, not Beijing'

By Howard B. Owens
Remote video URL

The pandemic exposed a weakness in the U.S. economy, Sen. Charles Schumer said today while at a car dealership in Genesee County -- not enough computer chips are manufactured in the U.S., leading to a shortage in the semiconductors that help cars, along with phones, computers, and appliances, run.

Currently, only 12 percent of chips are manufactured domestically, according to Schumer, compared to 37 percent in the 1990s.

Many foreign competitors, including China, are investing heavily to dominate the industry, Schumer said. Nearly 75 percent of global semiconductor production is now occurring in East Asia, and foreign government subsidies drive the majority of the cost difference for producing semiconductors overseas and in the U.S.

In response, Schumer, the majority leader in the Senate, introduced the CHIPS and Science Act, which with the president's signature this past week, is now law.

It provides over $50 billion in federal incentives to get more chips made in the U.S.

"We say (in the bill), not only do they have to make the chips here, but they can't make any more of them in China," Schumer said. "That is very, very good for America. We're saying we want to build the future in Batavia, not Beijing, in Syracuse, not Shanghai. So I wrote this legislation with upstate in mind."

Schumer is bullish on WNY STAMP, the 1,250-acre technology park that is now shovel-ready in the Town of Alabama.  He believes that before long, there will be a semiconductor plant at the park.

"Companies are seeing upstate New York is the place to be," Schumer said. "We hope there'll be many more. And we're fighting very hard to get one at STAMP. It is seen as a great opportunity at some of the chip companies -- I'm not allowed to say who -- but they have already visited here a couple of times. The bottom line is that manufacturing chips here in New York has the potential to be our 21st century Erie Canal."

He promised to do everything he can to attract chip manufacturers to upstate New York.

"We have more shovel-ready sites, including the STAMP facility right here in Genesee County than any place in the country," he said. "I'm gonna use my clout as majority leader in making (upstate New York) the center of the country with $5 billion of federal money for all of our semiconductor advanced research and development, which attracts people here. We have a great workforce here. We have great universities here. We have cheap water and cheap electric power, which these chip plants need as well, so you put that all together, and we are ideally suited now that this bill passed."

From a press release, highlights of the legislation:

Specifically, Schumer highlighted that the bill includes:

  • $39 billion for the CHIPS for America Fund to provide federal incentives to build, expand, or modernize domestic facilities and equipment for semiconductor fabrication, assembly, testing, advanced packaging, or research and development to help attract major chip manufacturers to shovel-ready sites like STAMP in Genesee County.  
  • $11 billion for Department of Commerce research and development including creating a National Semiconductor Technology Center (NSTC) a public-private partnership to conduct advanced semiconductor manufacturing, with Albany Nanotech primed to be a top contender to serve as a major hub for the NSTC, and other specialized R&D programs that universities across the state are in a strong position to compete for.
  • $2 billion for the DoD CHIPS for America Defense Fund.
  • $200 million for the CHIPS for America Workforce and Education Fund to kick start the development of the domestic semiconductor workforce, which faces near-term labor shortages, by leveraging activities of the National Science Foundation.
  • A new Investment Tax Credit for semiconductor manufacturing facilities and equipment.

Schumer explained that New York is uniquely suited to take advantage of these federal investments to reassert America’s global technological leadership. New York is currently home to over 80 semiconductor companies that employ over 34,000 NY workers, including global industry leaders like GlobalFoundries, Wolfspeed, onsemi, IBM, and other major microchip and innovation companies that support them like Corning Inc. in Monroe County which just announced a $139M, 270 job expansion in anticipation of this bill. Schumer said investments like these are only the beginning though, and now that his bill has finally become law, the ripple effects from more chip fabs and their supply chains being built in places like Upstate New York will give companies like Baxter and the American economy the stability it needs to avoid shocks like this again in the future. 

Jacobs votes for bill that could help land semiconductor company at STAMP

By Press Release

Press release:

Congressman Chris Jacobs (NY-27) released the following statement after voting in favor of H.R. 4346 – CHIPS-Plus. This legislation passed the House of Representatives in a 243-187 vote and passed the Senate earlier this week 64-33.

“The COVID pandemic highlighted our overdependence on China, especially in terms of semiconductor chips which are now critical components in nearly every product and machine impacting our daily lives. China holds a major share of this market, and should they ever take over Taiwan - which is another major producer of semiconductors - our nation’s supply would be in jeopardy,” Jacobs said. “We need to urgently ‘re-shore’ chip manufacturing and bolster domestic production, this legislation will make that possible.”

“CHIPS-Plus also presents an opportunity for our region. The City of Buffalo has an opportunity to land one of the twenty tech hubs established in the bill and Genesee County has a great potential to land a semiconductor manufacturer. This could mean numerous high paying jobs and a transformational leap for our regional economy,” Jacobs said.

“This legislation is a bipartisan achievement for our economy and our nation’s security – I am proud to have voted for it, and look forward to it being signed into law,” said Jacobs.

Previously: Genesee County will benefit from $50 billion CHIPS and Science bill passed by Senate, Schumer says

Photo Courtesy GCEDC: Aerial view of Plug Power plant under construction at WNY STAMP

Genesee County will benefit from $50 billion CHIPS and Science bill passed by Senate, Schumer says

By Howard B. Owens

Every part of Upstate New York, including Genesee County, will benefit from his bill to spur development in computer chip and technology manufacturing, Sen. Charles Schumer said today during an online press conference with reporters from throughout New York.

Upstate has more shovel-ready business park sites than any other region in the nation, and WNY-STAMP is among those sites drawing interest from semiconductor manufacturers with the likely passage of this bill, Schumer said.

"There are a whole number of companies that were thinking of going overseas to Europe or to Asia, that with this bill have now said they're going to locate in the United States," Schumer said in response to a question from The Batavian. "We have some of the great sites including the STAMP site in Batavia and we're going to do everything we can to lure them. And remember, they depend on the Commerce Department to get some grants for this. These are large grants, and I am going to, as Majority Leader, I think, I'll have some say with the Commerce Department."

The CHIPS and Science Act of 2022 creates $50 billion in funding designed to provide financial assistance to chip manufacturers and other technology companies to build factories in the United States.

The bill passed the Senate today and Schumer, who authored the bill and has doggedly pursued it for a long time, said it will easily pass in the House of Representatives.

Schumer pushed for passage, he said, because the U.S. must beat China in chip manufacturing and because he believes spurring innovative growth in high-tech will benefit all of New York, especially Upstate New York.

"I wrote this bill with the future of Upstate New York in mind," Schumer said. "The bill creates $50 billion in federal incentives to bring semiconductor manufacturing back to the US. And guess what place in America is most suited to get these plants? Upstate New York. There are places in Albany and Syracuse and Western New York that have shovel-ready sites that the big tech companies are already looking at for new chip fabs."

So far, China has been winning the chip manufacturing war, Schumer said. He wants to shift the momentum back to the United States.

"It's time to build our future in Syracuse, not Shanghai; in Buffalo, not Beijing," he said.

He said the odds are high that semiconductor manufacturers are going to look to Upstate New York for their new plants, which will employ thousands of people in high-paying jobs.

"We're gonna go all out and we're going to beat China," Schumer said.

WNY STAMP, located in Alabama near the intersection of Route 77 and Judge Road, is more than 1,100 acres set aside for advanced manufacturing.  GCEDC has been pursuing tenants for the park for more than a decade, and after coming close with 1366 Technologies in 2015 (a project that failed, according to sources, because of then Rep. Chris Collins' unwillingness to support it), the IDA succeeded last year when Plug Power agreed to make a $232.7 million investment to build a new hydrogen fuel plant at the site.

Steve  Hyde, president and CEO of GCEDC, said the agency is pleased with the passage of the bill.

"Senate Majority Leader Schumer has long-championed upstate New York as the ideal region for critical growth of the domestic semiconductor manufacturing and R&D investments due to our university research and talent, our established and ever-growing semiconductor supply chain, along with our considerable capacity of renewable, reliable, and competitively priced electricity," Hyde said in a statement. "We applaud Senator Schumer for his leadership, and stewardship in getting Congress to pass the Chips and Science Bill, which will be the catalyst to growing the high-tech economy at the Western New York Science & Technology Advanced Manufacturing Park (STAMP) and all across upstate New York."

For all prior coverage of WNY Stamp, click here.

For a press release from Sen. Charles Schumer with more details about the bill, click here.

UPDATE:  The Hill is reporting that because of a deal between Sen. Joe Manchin and Sen. Charles Schumer on a reconciliation bill, Republican members of the House of Representatives will now, as of Wednesday evening, oppose the CHIPS bill.

Top photo: Sen. Charles Schumer in a screenshot of today's press conference.

Aerial photo courtesy GCEDC showing Plug Power under construction and the WNY STAMP acreage. 

Schumer pushing to make NY leader in carbon-free energy production

By Press Release

Press release:

U.S. Senate Majority Leader Charles E. Schumer today launched a major push to make New York State home to the nation’s first Regional Clean Hydrogen Hub created by the bipartisan Infrastructure Investment & Jobs Law. In a direct letter to U.S. Secretary of Energy Jennifer Granholm, Schumer explained how New York is already a national leader in hydrogen energy production and research, with North America’s largest green hydrogen production facility currently being constructed in Western New York by Plug Power. Schumer said that if selected for federal investment, the Regional Clean Hydrogen Hub would mean thousands more clean energy jobs in New York and major federal investment to cement New York as a leader in the fight against climate change and the future of carbon-free energy production.

“From WNY, Rochester, and the Capital Region to Long Island, New York is leading the nation in hydrogen energy production sparking innovative research that is literally turning water into carbon-free power for electricity, fuel cells, and so much more. That is why I wrote to Energy Secretary Granholm directly to make it clear that New York has all the right ingredients to be the nation’s first-ever Regional Clean Hydrogen Hub and fuel America’s clean energy future,” said Senator Schumer.

Schumer added, “When I led the bipartisan Infrastructure Investment and Jobs Act to passage with an unprecedented $9.5 billion federal investment to expand the hydrogen industry, I had in mind innovative companies like Plug Power in Upstate New York and the potential to create thousands of good-paying clean energy jobs in communities that need it most. New York’s powerhouse workforce, top tier research institutions, and easy access to the renewable energy needed to produce green hydrogen make it uniquely suited to supercharge and lead the federal government’s efforts to secure the nation’s spot as a global leader in clean hydrogen production to power our fight against climate change.”

The bipartisan Infrastructure Investment and Jobs Act provided $8 billion for the Department of Energy to establish four or more Regional Clean Hydrogen Hubs to demonstrate the production, processing, delivery, storage, and end-use of clean hydrogen. Today’s two Requests for Information from DOE’s Office of Energy Efficiency and Renewable Energy points to how important it is that New York quickly coordinate the most compelling proposal for a New York-centered Hydrogen Hub. In addition, the law also makes several new critical investments in hydrogen fuel and clean energy, including:

  • $1 Billion for a new Department of Energy Electrolyzer demonstration, commercialization and deployment program to improve the efficiency, increase the durability, and reduce the cost of producing clean hydrogen using electrolyzers.
  • $500 million for a new Department of Energy clean hydrogen manufacturing recycling program to foster a clean hydrogen domestic supply chain in the U.S. 

Senator Schumer has been leading the charge to expand clean hydrogen production in New York. In 2020, Senator Schumer made a personal call to Plug Power CEO Andy Marsh pushing for the company to select Upstate New York for the site of its newest factory instead of a site in another state that was in contention.  In December 2020, Schumer announced that Plug Power had heeded his call and selected Monroe County as the site for its new ‘gigafactory,’ a hydrogen fuel cell component R&D and manufacturing plant, bringing $125 million and nearly 380 jobs to the Finger Lakes region. The new ‘gigafactory’ will manufacture hydrogen fuel cell stacks and electrolyzers, which will be used to power a variety of electric vehicles and to generate power from renewable green hydrogen.

Schumer also called on the Department of Energy to support Plug Power’s newly proposed plan to construct a $290 million hydrogen facility at the Western NY STAMP site in Genesee county and personally visited the site in September. Plug Power’s new production facility at STAMP will produce green hydrogen to supply fuel-cell-powered equipment and vehicles such as freight transportation and logistics handling equipment.

Schumer makes pitch to Israel-based semiconductor company to build plant at STAMP, or elsewhere upstate

By Press Release

Press release:

Following his continued advocacy to make Upstate NY a global semiconductor manufacturing hub, U.S. Senate Majority Leader Charles E. Schumer personally called Tower Semiconductor CEO, Russell Ellwanger, about the company’s interest in expanding their operations. Schumer urged the CEO to locate their next semiconductor fabrication (“fab”) plant in Upstate NY. Tower Semiconductor is currently considering New York, along with several other locations, for a new $5 billion semiconductor fab plant that would create up to a thousand jobs.

Schumer said New York boasts several sites across Upstate that are ready to be home to Tower’s next chip fab, from the STAMP campus in Western New York and the White Pine Commerce Park in Central New York, to Marcy Nanocenter in the Mohawk Valley and Luther Forest in the Capital Region.  Schumer added that Upstate New York boasts a thriving semiconductor ecosystem, top-notch universities, a world-class workforce, and a diversity of companies across the supply chain. 

“Tower Semiconductor’s interest in expanding its manufacturing operations in the U.S., and potentially in Upstate NY, is exciting news for the entire state and a potential game-changer for the region. I made it clear to Tower that I strongly support locating their new semiconductor chip fab in New York. I know firsthand Upstate NY has all of the ingredients to be a global epicenter for semiconductor manufacturing and that is why any of our multiple shovel-ready sites from STAMP in WNY, White Pines in CNY, Luther Forest in the Capital Region, and Marcy Nanocenter in the Mohawk Valley is the perfect location for Tower Semiconductor’s new chip fab,” said Senator Schumer. “Our world-class New York workforce and distinguished research institutions, coupled with New York’s considerable experience in semiconductor manufacturing and R&D mean Upstate NY is tailor-made to be the home for Tower’s new fab. I stand ready to help Tower in any way for investment in New York, including securing the federal semiconductor manufacturing and R&D incentives, and further cement New York as a global hub for chip manufacturing.”

Schumer has long emphasized the importance of active federal support for the semiconductor industry including his push to include provisions in the FY2021 NDAA to create new federal semiconductor manufacturing, R&D, and training programs, noting that even though the U.S. revolutionized the semiconductor and broad microelectronics industries and invented nearly all of the key technology used to this day, by 2030, non-U.S. competitors are projected to control 83% of the global semiconductor manufacturing supply while domestic production could be less than 10%, which would be a threat to national security and economic competitiveness.

In June, Schumer successfully passed through the Senate the U.S. Innovation and Competition Act (USICA), legislation he introduced that combined his Endless Frontier Act to make a significant investment in research, development, and innovation, other bipartisan competitiveness bills, and $52 billion in emergency supplemental appropriations to implement the semiconductor-related manufacturing and R&D programs the senator authorized in last year’s National Defense Authorization Act. USICA also created a program to support legacy chip production that is essential to the auto industry, the military, and other critical industries. Schumer is now working with the House to pass USICA, including the historic federal semiconductor incentives, into law as well as supporting the passage as part of the Build Back Better reconciliation bill of a new 25% tax credit for investments in domestic semiconductor facilities and equipment, modeled after the FABS Act. 

Tower Semiconductor is an Israel-based leading foundry of high-value analog semiconductor solutions and provides technology and manufacturing platforms for integrated circuits in growing markets such as consumer, industrial, automotive, mobile, infrastructure, medical and aerospace, and defense.

Samsung reportedly decides to build $17 billion semiconductor facility in Taylor, Texas.

By Mike Pettinella

Published reports today indicate that Samsung Electronics Co. has decided to build a $17 billion semiconductor plant in Taylor, Texas, ending speculation that South Korea’s largest company would be locating the facility in New York State and, possibly, at the Western New York Science & Technology Advanced Manufacturing Park in the town of Alabama.

A story from Bloomberg Wire stated the chip-making plant will be constructed in the Central Texas city, which is about 30 miles from Samsung’s giant manufacturing hub in Austin.

A news conference led by Texas Gov. Greg Abbott reportedly is scheduled for 5 this afternoon.

Sources close to the project said the plant would create about 1,800 jobs and chip production is expected to start at the end of 2024.

As late as September, U.S. Sen. Charles Schumer – during an appearance at STAMP to promote Plug Power’s decision to build a green hydrogen facility there – said that Samsung officials toured the 1,250-acre site owned by the Genesee County Economic Development Center and that he was communicating “on a regular basis” with the company’s president.

A resolution posted on the Taylor, Texas, website reveals that the city is offering Samsung more than $300 million in tax credits for the first 10 years – and additional incentives for two subsequent 10-year periods, plus a tax waiver of 92.5 percent on all new property built on the site for the first 10 years.

Town Board sets fire protection public hearing for Nov. 17, contracts with Alabama for STAMP code enforcement

By Mike Pettinella

A public hearing on the Town of Batavia’s 2022 contract with the Town of Batavia Fire Department is scheduled for 7 p.m. Nov. 17 at the Town Hall, 3833 West Main St. Rd.

The proposed contract, which would take effect on Jan. 1, calls for the town to pay the fire department $1,185,265 for fire protection for all of next year.

Town residents fund the fire department through a separate special district tax, which is expected to remain at $2.34 per thousand of assessed valuation – the same as 2021.

The town board announced the public hearing date at its meeting on Wednesday night.

In other action, the town board:

  • Approved an agreement in which the town will provide code enforcement services to the Town of Alabama, specifically for development at the WNY Science & Technology Advanced Manufacturing Park.

According to the resolution, the Town of Alabama shall pay the Town of Batavia $55.44 per hour during normal business hours Monday through Friday. The charge for field inspections outside of that timeframe will be $83.16 per hour. Mileage incurred by enforcement officers also will be reimbursed.

  • Completed the preliminary 2022 budget process, setting the property tax rate at $2.51 per thousand of assessed valuation. The rate is a 12 percent decrease from 2021, and will generate $1,236,000 in property taxes – the same amount as last year.

The sewer rate remains the same as 2021 -- at $7.09 per 1,000 gallons used -- while the water rate for both residential and agricultural consumers is going up by 2 percent – to $6.32 and $5.12 per 1,000 gallons, respectively.

Salaries for elected officials are as follows:

  • Supervisor Gregory Post, $40,000.
  • Deputy Supervisor Dan Underhill, $18,000.
  • Council members Patti Michalak, Chad Zambito and Sharon White, $12,000.
  • Town Clerk/Tax Collector Teressa Morasco, $74,541.
  • Highway Superintendent Tom Lichtenthal, $20,101.
  • Town Justices Lisa Funke and Andrew Young, $28,840.

No one from the public spoke at public hearings on the budget, sewer and water rates on Wednesday.

Gov. Kathy Hochul at WNY STAMP: Plug Power will get 'the very best people'

By Mike Pettinella

Gov. Kathy Hochul touted the hard working Western New York community today as she took part in a groundbreaking ceremony to recognize Plug Power, Inc.’s $290 million investment at the Science & Technology Advanced Manufacturing Park in the Town of Alabama.

“There is a strong work ethic here,” said Hochul, a Buffalo native who spent much time in Genesee and surrounding counties during her days as a U.S. Congresswoman and New York State lieutenant governor. “I come from just a little bit down the road – the granddaughter of a steel worker in a steel plant; my dad worked in the steel plant. In Rochester, he worked at Eastman Kodak and many other jobs.

“People are used to working hard, and employers are recognizing it. This is in our DNA. This is what they will get when they come here and invest here. They’ll get the very best people.”

Hochul was joined by Andy Marsh, chief executive officer of the Latham-based Plug Power, which is set to construct a major green hydrogen fuel production plant and a 450-megawatt electric substation that will provide power to the entire STAMP site.

Officials from the New York Power Authority were also on hand at the Genesee County Economic Development Center-coordinate event, which drew around 100 people.

The NYPA board previously approved a 10,000-kilowatt hydropower provision along with $1.5 million in funding from the Western New York Power Proceeds program, and 143 MW of High-Load Factor power that NYPA will procure for Plug Power on the energy market, drastically lowering electric bills through a reduction in electricity delivery chargers.

Other speakers were State Sen. Edward Rath, Assemblyman Steve Hawley, Genesee County Legislature Chair Rochelle Stein and GCEDC Vice President of Operations Mark Masse.

A CLEAN ENERGY REVOLUTION

Hochul said that the location “is the place where the clean energy revolution is happening.”

She thanked officials at the NYPA for “harnessing the power of the Niagara River … and (being able to) spread that energy across the state – literally, spread the energy across the state.”

“To invest here and to send a message that this project is important enough to have your investment, but also to transfer electricity here and power here, and the conversion into green hydrogen. That’s not happening anywhere else; nowhere else are they being that creative,” she said.

She drew a round of applause when she said, “It’s happening here in Genesee County. And as a result, we’ll have North America’s largest green hydrogen production facility here in the State of New York, but right here in Genesee County.”

The governor said she was “so delighted” to be back home again as this county has special meaning to her.

“I heard Mark (Masse) say I was here a few times,” she said. “I was here a few times a week – to your candy stores and your shops and your restaurants and your downtown, and had the opportunity to talk about the Downtown Revitalization Initiative and so many other transformative projects. So, when I come back home here it gives me the sense of not just (being) excited about what we’ve done in the past but the possibilities in the future. And, ladies and gentlemen, the future is starting today.”

THANKING THE 'EARLY VISIONARIES'

She credited “early visionaries” such as Steve Hyde, former Senator Mary Lou Rath, Assemblyman Steven Hawley, Genesee County Legislature Chair Rochelle Stein and local government officials.

“Thank you for never giving up, for always having the faith. Your persistence and patience has paid off. And that’s what today is all about.”

And she thanked Marsh for seeing the possibilities in Genesee County.

“It’s companies, it’s people and it’s also places, and this place has been crying out for an opportunity like this to show what it was really made out of,” she said. “And the location, I’ve always said this. This region is spectacular because of its proximity to two larger urban areas …”

Masse said interest in STAMP from corporate site selectors from the advanced manufacturing sector -- including semiconductor and clean energy -- has never been stronger.

“There’s a long queue of prospects constantly asking for information, meetings and visiting the site. Our region and our site are very suitable for companies such as Plug Power to succeed and make a lasting impact,” he said.

MASSE PROMOTES SHOVEL-READINESS

Noting that the region has 2.1 million people in a 60-mile radius with 57 colleges and universities – and 4,000 engineering graduates annually, Masse said, “The only thing holding us back now is the increasing of our capacities of existing infrastructure to make this site completely shovel-ready.”

“This would have the full water, sewer, electric at the property line for any company looking to locate here so they can move quickly to construct their facility and be up and running as soon as possible.”

Masse said he was hopeful that New York State will continue to make infrastructure investments to advance the shovel-readiness of mega-sites such as STAMP.

Marsh compared Plug Power’s expansion to George Westinghouse’s pioneering electrical network more than 100 years ago.

“Hydrogen is really important, and green hydrogen is especially important,” he said, adding that projections show that 18 percent of the world’s energy is going to come from hydrogen.

MARSH FORESEES ACCELERATION

“And right here in the field will be the first large-scale green hydrogen network, not only in New York, not only in the U.S., but around the world. Just like George Westinghouse did with electricity years and years ago.”

He called that “a great accelerator for this local economy and Plug Power believes, with its investments here, which we hope to continue to grow – with our investments in Rochester – we will see the same.”

Marsh, mentioning that Plug Power’s green hydrogen will power forklifts at several big companies, said that 25 percent of food during COVID moved through Plug Power products.

“It really made the world realize what Plug Power was doing. We were able to raise $5 billion in the public market, which supplements a lot that goes on with support in New York and other places,” he offered.

CLICK HERE for more about today's developments.

Photo above: Gov. Kathy Hochul speaking at this morning's Plug Power groundbreaking event at WNY STAMP in the Town of Alabama. Photos below: Hochul and Plug Power CEO (center) and other regional and state officials take part in the ceremony; state, regional and local government leaders turned out for the event. Photos by Steve Ognibene.

Settlement between Tonawanda Seneca Nation, GCEDC removes 200 acres at STAMP from possible development

By Mike Pettinella

Press release from Tonawanda Seneca Nation:

GENESEE COUNTY, New York — The Tonawanda Seneca Nation reached a settlement (with the Genesee County Economic Development Center) of a lawsuit seeking to stop Plug Power, Inc.’s construction of a facility that would anchor a manufacturing megasite, known as the STAMP (Science & Technology Advanced Manufacturing Park) site. In June, the Nation petitioned the New York State Supreme Court to stop the development of the Plug Power project adjacent to the Nation’s land in Genesee County, but a judge dismissed the case on procedural grounds last week. The STAMP site is adjacent to the Nation and within the Nation’s ancestral territory.

“We’re disappointed that the court didn’t have the opportunity to hear our arguments in this case,” said Kenith Jonathan, Sachem Chief for the Wolf Clan of the Tonawanda Seneca Nation and keeper of the Western Door. “We never got our day in court to explain how the project would diminish the Big Woods and have a negative impact on our Nation and our way of life.”

In its petition to the court, the Nation warned that the development would diminish the Big Woods, a pristine parcel of land that citizens of the Nation forage and hunt on, as they have for centuries. The Big Woods is a source of various traditional medicines important to the Nation’s culture and health. For centuries, the Tonawanda Seneca people have relied on the medicines, passing down that knowledge from generation to generation. Tonawanda Seneca citizens also play traditional games not far from the proposed Plug Power site. Citizens of the Nation voiced concern that the games would be disturbed by the traffic, noise and light pollution from the project.

“Make no mistake; we are opposed to developing a manufacturing megasite adjacent to pristine woods on undeveloped land,” said Chief Jonathan. “While we are disappointed that the construction will go forward, this settlement includes important protections to reduce the impact on our Nation and to protect our way of life. We are hopeful that the agreement can be the framework for a more collaborative relationship with GCEDC and Plug Power moving forward.” 

The settlement negotiated by the Nation will permanently protect from development over 200 acres of land on the STAMP site that is adjacent to the Nation’s territory. Plug Power, Inc. also is prohibited from using pesticides on the protected lands, which will further protect the environment. The Nation also will have cultural resource monitors onsite during earthmoving activities — to help identify and protect any unanticipated cultural resource discoveries.

County judge rejects Tonawanda Seneca Nation's suit against GCEDC in connection to Plug Power siting

By Mike Pettinella

A lawsuit filed by the Tonawanda Seneca Nation challenging the Genesee County Economic Development Center’s State Environmental Quality Review determination in connection with the Plug Power, Inc., project has been dismissed by Genesee County Acting Supreme Court Justice Charles Zambito.

The nation contended that the liquid hydrogen facility, which is in line to become operational sometime next year at the Western New York Science, Technology and Advanced Manufacturing Park in the Town of Alabama, would infringe upon its “Big Woods” sacred ground that is situated near the western end of STAMP.

As plaintiff in the legal action, the nation also sought to prove the GCEDC did not provide notification prior to the completion of the environmental review process.

Zambito, in his decision released on Sept. 28, ruled that the Seneca Nation failed to add Plug Power, Inc., as a defendant prior to the statute of limitations.

GCEDC reported its environmental impact determination on Feb. 4, giving the nation four months to amend its original suit of June 4 that listed only the GCEDC two top officers and board chair and vice chair as defendants.

The nation eventually added Plug Power, Inc., as a defendant on June 18 – two weeks after the deadline. Furthermore, it did so without “leave of the Court,” Zambito wrote, causing a delay in the amended petition’s filing until July 26.

In his analysis, Zambito wrote that “the proposed amended petition is untimely as it relates to Plug Power, Inc. (deemed a “necessary party”) and the individual GCEDC respondents. The motion to amend is denied accordingly and the amended petition is dismissed.”

He also dismissed the original petition for failure to include Plug Power, Inc., ruling that while the original petition was filed in a timely fashion, “the failure to join such a necessary party can result in the dismissal of the action.”

According to the GCEDC, Plug Power, Inc., plans to build the $232.7 million green energy technology facility at a 29.884-acre site at STAMP, with a proposed initial operation creating 68 new jobs at an average salary of approximately $70,000.

The Latham-based company also will invest $55 million to help build a 345/115KV electric substation in partnership with the New York Power Authority and National Grid. The substation will support future expansion and growth opportunities at STAMP’s 1,250-acre mega-site.

The GCEDC board of directors have approved the following incentives to Plug Power, Inc.:

  • Approved Property Tax Payments (Payment in Lieu of Taxes): $2.3 million per year, $46 million over 20 years.
  • Sales Tax Exemptions: $1.1 million.
  • Estimated Savings: $117.7 million property tax savings over 20 years if assessed at cost of construction ($232.7 million).
  • Anticipated assessment is much more likely to be $60-90 million. Payments of $2.3 million per year equate to a zero percent abatement on a $65 million assessment.