Skip to main content

infrastructure

Noonan Drive will be closed during milling work

By Howard B. Owens

Press release:

Noonan Drive will be closed on Thursday, July 13, between the hours of 7 a.m. to 3 p.m. for cold milling operations.

While work is being performed in this area, the roadway will be closed to all through traffic. Local traffic will be permitted to and from their residence/property but should plan accordingly for delays.

All residents/businesses within the work area are asked not to park on the roadway during cold milling operations.

This is weather-dependent work. If work is postponed, it will progress next on the work day. Please, plan accordingly and contact the Bureau of Maintenance with any questions. Thank you for your cooperation in advance. 

Two avenues in Batavia to close next week for repairs

By Maria Pericozzi

Press release:

Buxton Avenue in Batavia will have road closures between 7 a.m. and 3 p.m. on June 26.

Verona Avenue in Batavia will have road closures between 7 a.m. and 3 p.m. on June 27.

While work is being performed, the roadways will be closed to all through traffic. Local traffic will be permitted to and from their residence, but people should plan accordingly for delays.

All residents within the work areas are asked not to park on the roadway during the day.

This is weather-dependent work. If work is postponed it will progress the next workday.

Please, plan accordingly and contact the Bureau of Maintenance with any questions.

Thank you for your cooperation in advance.

Pembroke, Byron bridges to be replaced through BRIDGE NY program

By Maria Pericozzi

Through Gov. Andrew Cuomo’s BRIDGE NY program, Genesee County received two grants to rebuild two local bridges in Pembroke and Byron.

According to the governor’s website, the state is making $200 million available in enhanced assistance for local governments to rehabilitate and replace bridges and culverts statewide.

The Pratt Road bridge over Tonawanda Creek in Pembroke was structurally red flagged and load posted for 5 tons.

Highway Superintendent Tim Hens said the bridge over Tonawanda Creek is one of the top bridges in terms of need for replacement.

“It’s not a high-volume road,” Hens said. “But it is a key connector.”

The bridge replacement will be $178,000, with 95 percent being federally funded. 

The Searles Road bridge over Spring Creek in Byron will also be replaced.

Hens said the capital project established would amount to $133,000 for the Searles Road bridge, with 95 percent being federally funded.

This fall they will go through the design process and both bridges should be ready for construction in 2018.

“By time the state executes their part of the grant, the clock starts ticking,” Hens said. “We have to have the bridge under construction in 18 months.”

East Avenue to be closed at Elm Street on Wednesday due to city sewer project

By Billie Owens

Press release from the city's Department of Public Works:

East Avenue will be closed at Elm Street on Wednesday, June 14th, due to the sewer project beginning on Elm Street.

It is expected that the closure will be in place at 7:30 a.m. and continue until midafternoon. Motorists are encouraged to avoid this intersection by using East Main Street and North Street during construction.

Photos: Culvert replacement on Creek Road, Batavia

By Howard B. Owens

Creek Road near Lehigh Avenue, Batavia, is closed for culvert replacement.

Even though signs warn of the closure as far back and East Road, people are still driving all the way down to the barriers, even semi-trucks, according to a Creek Road resident, who thought it might be a good idea to remind residents of the closure.

The closure started Wednesday and is expected to last for seven to 10 days.

City to host meeting tonight on new water main on Vine Street

By Howard B. Owens

Press release:

The Department of Public Works will be holding an informational meeting regarding the scheduled installation of new water main on Vine St (East Main to East Ave), Chase Park (Vine St to Elm St), and Elm St (Chase Park to East Ave), and the installation of new sanitary sewer on Elm St (East Ave to North St) this year.

The meeting will be held Thursday, May 11, 2017 at City Hall, in the 2nd floor Board Room at 6:00pm. A brief project overview will be given with staff available to answer questions and review the construction plans. 

Ranzenhofer touts infrastructure spending in state budget

By Howard B. Owens

Press release:

State Senator Michael H. Ranzenhofer has announced today that the new budget will help to jump-start more infrastructure improvement projects throughout Western New York. The 2017-18 State Budget allocates $29 billion for transportation funding, representing a nearly $2 billion year-over-year increase.  

“The new budget delivers Upstate New York’s fair share of state transportation dollars and commits a record level of funding for critical projects. This funding boost will help to improve the condition of our infrastructure and strengthen our economy,” Ranzenhofer said.

The new budget increases funding by:
• $1.5 billion to accelerate statewide road and bridge projects;
• $65 million for local infrastructure repair projects; and
• $50 million for the local Bridge NY program.

A total of $603 million in funding will help municipalities with additional infrastructure improvement projects. The budget allocates $438 million for the Consolidated Local Street and Highway Improvement program (CHIPS), $100 million for the Pave NY program and $65 million for the Extreme Winter Recovery program.

“A record level of state funding will be going directly to local governments to help with repairs to improve Western New York’s highways, roads and bridges. Our crumbling infrastructure has been rated poor in the past. This funding is desperately needed,” Ranzenhofer said.
 

Genesee County

Municipality

2016-17 Budget* ($)

2017-18

Budget** ($)

Year-over-year Change ($)

Percent Change

City of Batavia

379,842

425,876

46,034

12.12

Town of Alabama

105,551

121,796

16,245

15.39

Town of Alexander

109,523

126,130

16,607

15.16

Town of Batavia

127,274

146,125

18,851

14.81

Town of Bergen

60,626

69,819

9,193

15.16

Town of Bethany

96,001

110,065

14,064

14.65

Town of Byron

118,132

136,721

18,589

15.74

Town of Darien

129,420

149,353

19,933

15.40

Town of Elba

94,073

108,934

14,861

15.80

Town of Le Roy

123,035

141,741

18,706

15.20

Town of Oakfield

62,166

71,370

9,204

14.81

Town of Pavilion

127,126

146,205

19,079

15.01

Town of Pembroke

117,583

135,045

17,462

14.85

Town of Stafford

116,921

134,716

17,795

15.22

Village of Alexander

10,920

12,522

1,602

14.67

Village of Bergen

24,213

27,495

3,282

13.55

Village of Corfu

16,418

18,971

2,553

15.55

Village of Elba

10,989

12,478

1,489

13.55

Village of Le Roy

91,833

105,458

13,625

14.84

Village of Oakfield

34,468

39,646

5,178

15.02

County of Genesee

2,056,583

2,297,067

240,484

11.69

 

Water main repair planned on Tracy Avenue, Batavia

By Howard B. Owens

Press release:

On Wednesday, March 1, the City of Batavia Water Department will be repairing a water main on Tracy Avenue starting at 9 a.m. The water will be turned off on Tracy Avenue from Hart Street to North Street.

We will keep water service interruption to a minimum. This work may result in a period of discolored water in this general area after service is restored. Residents should check to make sure water clarity has returned before resuming activities such as laundry, which may be impacted. 

DOT planning informational session about reconstruction of Bethany bridge

By Howard B. Owens

There will be an informational open house at Bethany Town Offices from 1 to 4 p.m., Wednesday, about the planned reconstruction of the Bethany Center Road Bridge over Route 20 in Bethany. CORRECTION: Time is 4 to 6 p.m.

There are no formal presentations, but NYT Department of Transportation engineers will be on hand to share details of the project and answer questions about the scope of the work, impact on travel during the six-month construction period, and other concerns residents might have about the project.

The current bridge was built in 1932 and is marred by cracking and crumbling cement and exposed rebar.

The new bridge is expected to have a functional life of at least 75 years and have two standard lanes that are 11-feet wide and shoulders with railings that are six-feet wide.

The $1.4 million project is expected to begin construction in the spring of 2018 and be completed by the fall of 2018.

Since Bethany Center Road ends three miles south of the bridge, detour signs will not be posted. There are parallel alternative routes.

When the current bridge is demolished, Route 20 will be closed for about two weeks. The detour will be Old Telephone Road, which runs parallel to Route 20.                

Photo: Water main break on Edgewood Drive, Batavia

By Howard B. Owens

More than dozen homes on Edgewood Drive, Batavia, are affected by a water main break today.

Town of Batavia crews are on scene and repairs will take up to two or three more hours.

UPDATE 6:30 p.m.: Supervisor Gregory Post informed reporter Mike Pettinella, an Edgewood Drive resident, that the main valve has been installed, and for all homeowners affected by the situation to turn their cold water on and let it run for 10 minutes to rid it of any possible discoloration. Crews are filling the large hole with stone, and have placed cones around the site as they continue their time on the job -- nearly nine hours.

UPDATE 3:15 p.m. Sunday, Nov. 27.: Supervisor Post is on the scene, and indicated that corrosion caused a main valve to malfunction. A new valve has been delivered to the scene and crews are in the process of installing it and reconnecting it to the water line.

Photo: Paving Summit Street

By Howard B. Owens

With paving underway today, the $2.5 million reconstruction project for Summit Street is near completion for the major portion of the work. There are still trees to plant and other finishing touches that need to be done; crews could wrap the major work up today.

Summit Street infrastructure project expected to be done by the end of next week

By Billie Owens

The $2.5 million Summit Street reconstruction project that started this summer in the heart of the city is winding down and Matt Worth, the city's Department of Public Works superintendent, says he expects everything to be completed week's end.

By contract, the work has to be "substantially done" by the end of the month, that's Monday. 

Worth said putting down the black top will technically substantially complete the project. Though that task is "a little weather-dependant, the forecast looks like that will be happening Monday."

Next is the completing the landscaping.

Thirty trees were removed because they conflicted with installation of curbs and sidewalks, or they were in a deteriorated condition. Sixty-two new trees are being planted. Worth added that this is an ideal time to plant the trees, according to the nursery they are working with, and it's apparently good to wait for the trees to become dormant for the season before planting them.

Grass seeding has been completed on the east side, and the finishing touch to the landscaping-- grass seeding on the west side -- will be done by Friday.

Also, crosswalks and stop bars will need to be painted on the fresh asphalt.

"We're really looking to bundle this up, so by the end of next week, I believe those things will have occurred," Worth said.

The Rochester engineering firm of Erdman Anthony has been supervising independent contract companies on this locally administered federal-aid project.

Workers removed the old road, put in new storm, sewer and drainage systems, and paved the road. Federal and state funds covered all but about $100,000 of the cost, with the city responsible for the rest.

The city also funded a $350,000 project to install new water main on Summit Street.

Our news partner WBTA AM/FM contributed to this story.

For previous coverage about the city's infrastructure projects this year, click here.

City repairing fire hydrant on Redfield Parkway

By Billie Owens

Today, Oct. 6, the City of Batavia Water Department is repairing a fire hydrant on Redfield Parkway. Work began at 9 a.m. The water will be turned off on Redfield Parkway from West Main Street to Richmond Avenue. The city will keep water service interruption to a minimum.

This work may result in a period of discolored water in this general area after service is restored. Residents should check to make sure water clarity has returned before resuming activities such as laundry which may be impacted.

Town of Darien seeks USDA aid for $24 million water infrastructure project

By Billie Owens

Press release:

The Town Board of the Town of Darien has filed an application for grant and loan assistance with USDA Rural Development for a Water District #6.

This application has been accepted and has been moved to the funding process. The total cost of the project is estimated at $24,880,000. The Town anticipates receiving a grant of approximately $6,800,000 and the balance in the form of a low-interest loan from the USDA Rural Development Agency. 

The project will involve:

  • The installation of approximately 375,000 linear feet of water main along all Town roadways not currently provided with public water service;
  • The erection of a 300,000-gallon water storage tank, and a 500,000-gallon storage tank;
  • The installation of a pumping station;
  • and the upgrading an existing pumping station.

The project will serve 776 residential households within the Town. Consistent with Town Law and the procedures of Rural Development, the Darien Town Board will conduct public information meetings prior to making a commitment to undertake the proposed project.

Due to anticipated large attendance, the Public Information Meetings will be held at the Darien Volunteer Fire Department at 7 p.m. on Wednesday, Sept. 28 and at 10 a.m. on Saturday, Oct. 1. It is located at 10537 Allegheny Road, Darien Center.

David Hagelberger

Supervisor

Town of Darien

Tracy Avenue closed this morning for water line repair

By Howard B. Owens

Press release:

The City of Batavia Water Department will be making a repair on a broken water line on Tracy Avenue between Washington Avenue and North Street starting at 9 a.m. today. Tracy Avenue will be closed from Washington Avenue to North Street for all traffic. Please avoid Tracy Avenue until repairs are made. Water service may be interrupted on Tracy to make the repair.

Hawley announces more than $2m for Elba drinking water improvement project

By Billie Owens

Press release:

Assemblyman Steve Hawley (R,C,I-Batavia) today announced that the Village of Elba has been awarded more than $2 million to fund a drinking water improvement project that will help bolster the area’s clean water supply, fix and replace old pipes, sewer lines, treatment plants and assist with design and construction costs.

The grants are being distributed to various municipalities throughout the state as part of New York’s Water Infrastructure Improvement Act.

“Ensuring a clean and bountiful water supply for our citizens is one of the fundamental responsibilities of our state and local governments,” Hawley said. “Unfortunately, many pipes, sewer lines and treatment facilities were installed decades ago and were not made with the same durable materials we use today.

"As a result, New York’s infrastructure is failing, which places an extraordinary financial burden on local governments that are already handcuffed due to state mandates. I am pleased to see that the state has stepped up and is providing over two-thirds of the estimated cost of this project, which is vital for the health and well-being of our residents.”

Water main tie-in scheduled Friday at North and Summit in the city

By Billie Owens

Press release from the city's Department of Public Works:

A water main tie-in is scheduled for Friday, Aug. 5, on North Street at Summit Street. This is part of the Summit Street Reconstruction Project. This work will require North Street to be closed to traffic from Bank Street to Ross Street until the tie in is completed.   

Water service will be interrupted on North Street from Bank Street to Ross Street, Seneca Avenue and part of Tracy Avenue. Water service should be restored by early afternoon. 

This may cause temporary discolored water in the area or low pressure. Please check to make sure that water clarity has returned before doing any laundry or other activities which could be adversely affected.

Thank you for your cooperation.

Crews install new manhole today at State and Washington

By Howard B. Owens

Crews with Blue Heron Construction set a manhole today at Washington Avenue and State Street, park of the sewer reconstruction project this summer along Washington Avenue.

The area around Jefferson Avenue, Washington and State has been closed for a few weeks, but the project is getting closer to the finish line, said Matt Worth, director of Public Works.

Here's what Worth told us in an email:

They expect to be through the intersection tomorrow (State/Washington will open back up) and then the bypass pumping should no longer be required. Next week an additional crew is expected and it is anticipated that the new water and sewer services to the houses between Jefferson and State Street will be connected along with the unexpected water main work that is required on Jefferson Avenue.

If all goes well, everything west of State Street would then be back open (or very close) to traffic by the end of next week. This would leave construction between State and Bank and the storm sewer crossing on State Street to up near Park Avenue and final milling and paving (Ellicott Avenue to Ross Street) left to complete, with completion of the project before school is back in session.

Water leak forces shutoff in industrial park in Batavia

By Howard B. Owens

Water service has been shut off by the City of Batavia Water Department to businesses on Industrial Boulevard, Apollo Drive and Treadeasy Way.

Crews are repairing a water leak.

There is no ETA for when service will be restored.

Six streets in city slated for repaving in 2018

By Howard B. Owens

The city will receive $2 million in federal block grant money to repave six streets, Public Works Director Matt Worth told the City Council on Monday night.

The six streets will be milled and repaved at a cost of $2.5 million, and there may yet be some state money to help cover some of the cost difference.

The streets are Clinton Street, East Avenue, Liberty Street, South Liberty Street, Swan Street and Vine Street.

The city will now seek proposals from engineering firms, with the selection of the firm in the fall and then preliminary engineering work can begin. The final design would be completed in the fall of 2017 with work beginning in the summer of 2018.

Authentically Local