Skip to main content

Batavia Wastewater Treatment Plant

City and town of Batavia draft new wastewater agreement, HP Hood to proceed

By Joanne Beck
HP Hood expansion pic
2023 File Photo of HP Hood in Batavia.
Photo by Howard Owens

The city and town of Batavia have potentially come to an agreement about wastewater capacity, and HP Hood will be able to proceed with its $120 million expansion project that’s been halted since March, City Manager Rachael Tabelski says.

Hood’s project was, which involved a state environmental review, temporarily stalled when the city discovered that the town was in violation of a contracted wastewater capacity limit and had also taken on the lead agency role for the proposed expansion of process lines with no word to the city.

At that point, the city said the project cannot proceed, and it has been halted ever since. When asked about the project since then, Tabelski has said that “we are in active negotiations with the towns regarding a new purchase capacity agreement” and an agreement has now been reached.

“We will lift the SEQR challenge to the HP Hood project,” Tabelski said to The Batavian Monday evening, though the agreement still has to go through the official process of votes by the town board and City Council. 

Tabelski reviewed the new purchasing terms during Monday’s conference session. The town’s total wastewater flows average 1.4 million gallons per day at four total pump stations, which exceeds the town’s current contractual limit, Tabelski said. The current sewer capacity limit of the town is 850,000 GPD as established in the wastewater facility agreement of Feb. 23, 2015 between the city and town of Batavia.

A new agreement means the town can purchase an additional 350,000 GPD of treatment capacity for a total of 1.2 million for $1,382,500. If the town goes past the 1.2 million, a higher rate of purchase kicks in — the penalty rate — which serves as incentive for the town to remain at that 1.2 million output, Tabelski said. 

“We’re trying to incentivize them. We know they’re at 1.4, but we’re trying to get it down to 1.2,” Council President Eugene Jankowski Jr. said. 

Councilman Rich Richmond said that he was looking at the overage rates and believes “that’s a pretty good incentive.”

“So I want to thank you for doing this because I know, I heard how long it took, you had infinite patience, and you negotiated very well for the city,” he said. 

Jankowski asked if City Attorney George Van Nest reviewed the deal. He looked at it and worked with the city manager and assistant manager to ensure the numbers covered the city’s thresholds, he said. 

“I'm very concerned about making sure that we're within our operating limits, that we’re not pushing it too far, or as much as I love to help out, we only have so much capacity,” Jankowski said.

Jankowski preferred to move the vote to a future meeting so the council could get more public input rather than vote immediately, he said. The town of Batavia is expected to discuss the agreement at its next meeting on Sept. 18. 

At this time and until this agreement amendment is revisited, the town's total threshold will be 1,650,000 gallons per day max discharge. The city and town agree to meet every six months to review town flows to ensure that the town stays below the 1.65 GPD max discharge. If it is determined that the town has exceeded that amount, the city reserves all rights and remedies to protect the wastewater treatment facility permit. 

Does the city have enough capacity to maintain this additional amount for the town long-term? Is there a future solution?

“Town and city (of Batavia) have plans to move forward with a wastewater treatment plant growth study to support future development,” Tabelski said. “There is remaining capacity reserved for O-AT-KA, other city industries, and housing in the city of Batavia.”

Given the uncertainty regarding the wastewater treatment plant draft permit limits, the town will be solely responsible for funding an expansion study, which will be initiated as soon as practically possible. The city will act as project manager of the expansion study with a professional engineering firm of its selection and will bill the town as invoices are received.

In 1983, the city and town entered into a wastewater facility agreement that outlined the ownership and operation of the new treatment plant. In February 2015, they entered into a wastewater facility agreement and a wastewater metering agreement. The city currently owns 84.55% of the total plant capacity, and the town owns 15.45%. 

Due to ongoing development in the town, including the Genesee Valley Agri-Business Park, the town’s sanitary sewer flows are exceeding the contractual limit of .85 million gallons per day (MGD) or 15.45% of the total capacity, Tableksi said. 

Each city and town resolution in May 2023 identified the parties’ mutual concerns about potential increased flow resulting from the Kings Plaza pump station project, and the average sewer flow was 1.2 MGD. In fall 2023, the town advised the city that HP Hood was expanding but that it was only the warehouse and would not create additional demand for water or sewer capacity. Hood already discharges 1.1 to 1.2 MGD. By the end of 2023, the town’s average sewer flow had increased to 1.33 MGD, Tabelski said. 

“This is well in excess of the town’s contractual limit of .85 MGD,” she said. “Consequently, the town has no capacity to allocate to expansion of HP Hood or any other facility at this time.” 

The city also cannot permit increased sewer flows from the town of Batavia until the wastewater treatment plan expansion study is complete, she said. 

“The city and town still need to enter into a proposed wastewater agreement that was circulated in January 2024. However, this agreement will still not allow for increased discharge beyond 1.2 MGD. This pending agreement will be the town’s limit for wastewater discharge.”

As for its objection to the town being lead agency for the Hood project, Tabelski said that “the town has failed to accurately and timely inform the city about the expansion of wastewater capacity demand at the Ag Park.”

“In addition, the town is in breach of the wastewater agreement with the city by discharging in excess of .85 MGD,” she said. “A lead agent under SEQR is responsible for thoroughly and accurately evaluating the potential environmental impacts prior to making a determination of significance on the action.

“The town’s excess wastewater discharge beyond contract limits threatens the city’s discharge limits and has the potential to exceed the city’s (State Pollutant Discharge Elimination System) permit,” she said. “As a result, the city objects to the town’s lead agency designation for this action under SEQR.”

This has been a good week for Hood, which was named Dairy Plant of the Year. The Hood expansion is to be 32,500 square feet and pledges to create 48 new jobs while retaining 455 full-time equivalent jobs at the Genesee Valley Agri-Business Park. This project accommodates its automatic storage and retrieval system refrigerated warehouse. It will also include new batching and processing systems and other upgrades, which will allow the company to increase capacity and begin a new production line.

For prior coverage about this issue, go to wastewater.

Project's completion sets stage for normal operation at wastewater treatment plant, city manager says

By Mike Pettinella

The City of Batavia is doing all it can to “head off” the unpleasant odor that has been emanating recently from its Wastewater Treatment Plant, which is located behind the Industrial Park off Pearl Street.

With a $1 million capital project to replace the air header system at the WWTP completed, the ponds are receiving more oxygen and the “bugs” that breakdown the biological material are beginning to multiply again, City Manager Rachael Tabelski said in a response earlier today to an email from The Batavian.

“There will be a period of pond turnover where the organic material that was not broken down over the last several months is turned over or bubbles to the top of the ponds in an effort to digest it,” she wrote. “We sincerely hope that this post project period of turnover is only a short time and ponds go back to normal operations in the very near future.”

Tabelski reported that the city plans to conduct a headworks, capacity analysis and financial planning study for the WWTP and wastewater system in the near future.

The headworks is the first stage of the water treatment process. Its purpose is to remove large inorganic materials from the wastewater, with the goal to ensure the wastewater is free of toxins and debris when it reaches downstream equipment. 

The study, according to Tabelski, “will help us understand the long-term needs of the system and any other problem areas that need to be addressed so that we are operating at optimum efficiency and can continue to take waste from multiple industrial clients in the city and Town of Batavia.

Previously: Project at Batavia's Wastewater Treatment Plant is nearly complete

Project at Batavia's Wastewater Treatment Plant is nearly complete

By Press Release

Press release:

A Million dollar capital project to replace the air header system at the Waste Water Treatment Plant (WWTP) is nearly complete.  This morning the air delivery system was placed back in service for all three ponds serviced by the line.  

Over the next week, we are hopeful that there will be marked improvements of odors coming from the Waste Water Treatment Plant as the ponds recover from the previously compromised air supply.

The City advanced the project to the top of the capital improvement list for 2021, but supply chain delays delayed the project by about two months.  Upon material delivery, Keeler Construction Company of Albion, NY, worked an accelerated schedule to get the system back in service.  Other than the incidental, restoration the project is substantially complete.  

Flows from users with heavy constituents will be added back into the system gradually over the next few weeks to ensure that there is not a major impact on the system. 

City moving forward with upgrade to aeration system at wastewater plant

By Howard B. Owens

Press release: 

A Million dollar capital project to fix the air header system at the Waste Water Treatment Plant (WWTP) was approved by City Council at the beginning of April 2021.  After the design process was complete by GHD Group engineers, the City Department of Public Works bid out the project and City Council awarded the construction contract to Keeler Construction.

“The City advanced the project to the top of the capital improvement list for 2021 as it was determined that the air lines were degraded more than originally anticipated,” said Rachael Tabelski, City Manager, City of Batavia.  

The project will replace the air header system servicing the ponds.  The existing 30-year-old air header system was found to be compromised.  It is leaking a significant amount of air, and not delivering enough air to the ponds to efficiently digest waste.  These conditions have led to more odor in areas adjacent to the ponds. 

Currently, a temporary airline system is being used that introduces supplemental oxygen to the three primary wastewater ponds (attached graphic).   The temporary system is working on 50% capacity and will remain in place until project completion. 

“The City expedited the project; however the contractor had material supply chain issues in June and July.  These have been remedied and last week work on the site started up again.  Pond three airlines have been fully replaced and tested.  Keeler is moving swiftly to ponds one and two for replacement now,” said Ray Tourt, Acting Director of Public Works.

The material delays have set the project back by two months.  Manufacturers and distributors are struggling to make their commitments and this is one of the projects that was impacted by the disruption.  The project team of GHD Group, Keeler Construction and the City of Batavia are working to expedite the project and make up for lost time.  The City, at the request of the New York State Department of Environmental Conservation (DEC), has taken steps to mask and minimize odors until project completion.  

“The City continually revises complex capital improvement plans for infrastructure that includes the WWTP, water plant, sewer collection stations, water distribution lines, paved surface areas, vehicle and equipment as well as other City facilities.  The air header project was identified in recent capital plans and the City was able to reserve enough funds to begin the project in 2021,” said Rachael J. Tabelski, City Manager.   

History of the Waste Water Treatment Plant 

In 1990 treatment of waste began at the “new” wastewater treatment facilities which serves the City and a portion of the Town of Batavia. Completion of the new facilities represented the culmination of a long-term effort to provide upgraded treatment of wastewaters from the City and Town prior to discharge to Tonawanda Creek. At the time, the new facility enabled the City and Town's opportunities to expand their economic growth.

The WWTP is constructed on approximately 500 acres of land bordering the Conrail railroad tracks east of Donahue Road and north of Rose Road and replaced the City's old mechanical wastewater treatment plant, which was located on the south bank of Tonawanda Creek east of River Street.

Initial study and planning efforts focused upon upgrading or replacing the City's existing mechanical treatment facility with a similar facility. However, estimates indicated that the project costs, particularly with regard to annual operation and maintenance of the new facility, would place a tremendous burden upon the City and its customers.  A more cost-effective treatment system was devised whereby the City constructs the treatment process using a series of wastewater treatment lagoons instead of a mechanical treatment plant.

The lagoon system requires the use of a significantly larger land area and overall costs to the City was estimated to be one-third less than with a traditional plant upon construction.

Previously:

Weather, supply chain delays on maintenance work making for foul odor in some parts of Batavia

By Howard B. Owens

Bureau of Maintenance Superintendent Raymond Tourt today confirmed what many Batavia residents have been complaining about on social media for several days: foul ordors.

The odors were emanating from the ponds at the Waste Water Treatment plant and were more prevalent on Sunday and Monday, Tourt said in an email. 

Maintenance work at the plant has played a role but so has weather, Tourt said.

"Even with adding a supplemental air compressors the odor seemed to hang low and drift  further than the norm but this does happen on occasion even if we were not replacing the air lines," Tourt said. "These were hot and humid days and we think that the weather played a part in the ponds being noticed further from the WWTP.  

"It is unfortunate, but we have incurred delays of materials.  For this reason the contractor advanced the project as far as they could until the supply chain could catch up. Manufacturers and distributors are struggling to make their commitments and this is one of the projects that was impacted due to the supply line being disrupted.   

"All materials appear be at the site or have confirmed delivery to be delivered this week.  Work will resume on Monday  and optimistically will be completed through the months of August and September.  This project remains a priority and we would like to see it completed as soon as possible."

No time to 'waste': City moving quickly to replace inefficient air header system at water treatment plant

By Mike Pettinella

With a key component of the City of Batavia’s wastewater treatment plant operating at just 20-percent capacity, Maintenance Superintendent Ray Tourt says that it’s imperative to move up the capital project plan timetable to get it fixed.

“We desperately need to get that air back into the pond,” said Tourt at Monday night’s City Council meeting, talking about a faulty air header system at the plant. “We recognize how severe it is becoming.”

Tourt said the city has received about 10 years less than the expected 40-year life of the system, which introduces supplemental air to the three primary wastewater ponds.

In a memo to City Manager Rachael Tabelski dated March 29, Tourt wrote that “this air provides oxygen to the ponds to effectively digest waste.”

“Even though this project is scheduled for (this fiscal year), it was discovered that the system’s rate of decline is higher than originally anticipated,” he wrote. “For this reason, the project is being advanced as quickly as it can be.”

City Council acted favorably to his request, forwarding a resolution to contract with the lowest bidder to its April 26 Business Meeting. Opening of the bids is scheduled for April 19.

Tourt said work will be done in sections, starting with the large 16-inch line and working down to the six-inch line. He noted that the lines will be wrapped to prevent deterioration from the elements.

He said the system is leaking a “significant amount of air” and is creating a distinct odor near and around the ponds. Once that segment of an overall $1 million wastewater treatment plant project is finished – hopefully be the end of summer, he said crews will evaluate the plant’s compressors and diffusers.

In other action related to infrastructure, Council forwarded a resolution to apply for a Northern Border Regional Commission grant in the amount of $328,000 to partially fund a waterline project on Bank Street. The total cost of the project is approximately $410,000 but the city would be responsible for a local match of 20 percent ($82,000).

Tabelski, in a memo to Council dated April 6, wrote that work is needed “to improve water pressure and fire suppression capabilities on Bank Street, as well as enable future development on the City Centre campus and the Alva Place location for the (new) police station.”

She wrote that the Bank Street waterline will be expanded from its current four- and six-inch lines to an eight-inch line.

Massive operation underway to remove sludge from pond at treatment plant

By Howard B. Owens

It's taken 26 years for sludge to build up to about a three-foot depth in one of the processing ponds at the Batavia Wastewater Treatment Plant, but that buildup has reduced the pond's capacity by about 50 percent, so it's time to have it removed.

A removal project is now underway that costs about $1.3 million and is being conducted by contractors who specialize in sludge removal.

The process involves pumping the water-logged sludge out of the pond, screening it for large objects -- shoes, bottles, rocks -- and then sending it through one of two centrifuges, which use gravitational force and a polymer to separate the sludge from the water. The water is pumped back into the pond and the sludge is sent up a conveyor belt and dumped into a truck before it is hauled to a landfill.

Initially, the original estimate for the project was eight weeks, but a second centrifuge was added and now the contractor is processing a truckful of sludge every 90 minutes, to fill at least eight trucks a day, reducing the project timeframe to about four weeks.

Jim Ficarella, superintendent of water & wastewater for the City of Batavia, provided a tour of the project yesterday.

The water that has been squeezed from the sludge just before being piped back to the pond.

There will be about 2,100 dry tons of sludge removed from the pond.

One of the two centrifuges being used.

The pipelines that draw sludge from the pond and return water to the pond.

The screening process for removing large items that have inadvertently fallen into the pond.

The pond with sludge that has floated to the surface and been pushed by the wind to the eastern shoreline.

Ficarella said they know they won't get 100 percent of the sludge out of the pond, but they'll get most of it.

This pond is the second stage of the process. By this point, the wastewater has been at the plant for about three months. The whole process, which includes passing the wastewater through several ponds and a series of wetlands ponds, takes about a year. The clean water is pumped into Tonawanda Creek. 

See our previous story: Batavia Wastewater Treatment Plant, one of city's hidden treasures

The plant remains a birder's paradise, with birders traveling, literally, from all over the world, to visit the plant.

Town expected to pay $2 million to city for additional sewer capacity

By Howard B. Owens

The Town of Batavia needs to treat more wastewater these days, and possibly into the future, so it must purchase additional capacity in the treatment plant on Treadeasy Avenue.

If plans are approved, the town will pay the city nearly $2 million for an additional 500,000 gallons of capacity. 

The $2 million can be used by the city to repair and upgrade existing sewer lines or sewer-related infrastructure. Legally, it can't be used for anything else.

The treatment facility opened in 1990 with the intention that it serve both the town and the city. The total cost was $48 million, with $39 million being paid by state and federal grants. The city covered more than $8 million of the local share of the cost and the town more than $500,000.

For the price, the city obtained 3.5 million gallons per-day capacity and the town 350,000 gallons per day.

The town now occasionally exceeds its capacity, City Manager Jason Molino said, especially after two yogurt plants opened in the Genesee Valley Agri-Business Park.

Molino said the town also anticipates additional manufacturing growth, which means an even greater need for sewer capacity.

Residential growth, such as the new housing development on East Main Road, doesn't greatly increase the need for more capacity, Molino said.

The process of increasing capacity for the town will take up to 12 months, since the town is broken into sewer districts and there will need to be a series of public hearings before the town board can approve bonds to cover the $2 million expense.

The fee is based on a series of complex, and legally mandated, calculations that Public Works Director Sally Kuzon explained briefly for council members.

Previously: Batavia Wastewater Treatment Plant, one of city's hidden treasures

Batavia's Black Swan event

By Howard B. Owens

About a week ago, a black swan flew into the Batavia Wastewater Treatment Plant and has been hanging out ever since.

Black swans are native to Australia and it's highly unlikely this rare species made it to Batavia on its own.

The bird is likely an escapee of a private collection.

Because black swans were thought not to exist prior to the 18th Century, when they were unexpectedly discovered in Australia, statistician Nassim Nicholas Taleb named his theory of extremely rare events "black swans." (Recommend reading: Taleb's book "Fooled by Randomness.")

I spent more than 90 minutes this morning at the treatment plant, but with 20 mph winds, all of the big birds, including white swans and blue herons, not to mention the black swan, seemed to have sought shelter elsewhere.

A plant worker told me other photographers have been at the plant this past week and successfully captured pictures of the swan. I'll try again on a less windy day, but if a reader has a picture of this bird in Batavia they would like to share, please send it to howard at the batavian dot com (reformat, of course).

Meanwhile, I did get the picture below this morning of some ducks.

Photos: Public nature trails off Donahue Road, Batavia

By Howard B. Owens

When I did the story on the Batavia Wastewater Treatment Plant I didn't get around to taking a walk on the nature trails off Donahue Road, behind the plant.

The trails are maintained by the treatment plant staff and open to the public for hiking (no hunting, trapping or fishing allowed).

This even, I took Pachuco for a walk and brought my camera along. To give you idea of what's there, here are a few of the photos I took.

Batavia Wastewater Treatment Plant, one of city's hidden treasures

By Howard B. Owens

It's a place teeming with wildlife, a bit of a birder's paradise. It's 400 acres of accessible open space where local residents can walk their dogs, go for a jog or just enjoy a stroll along well-maintained paths.

Some might call it a park.

We call it the Batavia Wastewater Treatment Plant.

A lot of area residents, even if they know of the plant, may not know it's open to the public, or appreciate its natural aesthetics.

"It's great that the city is able to provide access to this great resource," said Tom O'Donnell, president of the Buffalo Ornithological Society. "It's a unique place to view waterfowl and shore birds."

Some 180 different species of birds have been spotted on the property during its 21-year history, including herons, loons, egrets, hawks, terns, swans and, of course, a variety of ducks and geese.

Birders from throughout the region know of the facility and have even traveled from as far away as Finland specifically to go birding in Batavia.

What makes the plant unique is the lack of reeds and trees between the birder and the birds, said O'Donnell. The vantage point, with the raised berms around the lagoons, give birders an exceptional angle to view waterfowl and shore birds.

It's tempting to call the fenced-in treatment plant a bird sanctuary, but it's prime function is to treat the city's effluent and turn it into something environmentally safe to pump back into the Tonawanda Creek.

The process is all natural -- no chemicals -- and it takes six to nine months for a molecule of water to pass from the facility's mechanical screen to the gravity outflow pipe near the pedestrian bridge at Walnut Street on the Tonawanda.

According to City Manager Jason Molino, the treatment plant is the largest lagoon system east of the Mississippi.

"That plant is a resource that I don’t think people understand," Molino said following a city council meeting last week. "It’s a special plant. It’s 400 acres. It doesn’t use chemical treatment. It’s natural treatment, so there’s no chemical cost. Only four people run it, seven days a week. You find me a sewer plant that has low labor costs like that, low treatment costs -- that's why our sewer rates are some of the lowest in Western New York."

And the plant is paid for. A combination of federal grants and municipal bonds helped get the plant constructed and the bonds are all paid off.

It even generates a little revenue (besides sewer-rate fees). A contractor pays up to $6,000 a year to harvest fat head minnows from some of the ponds. The minnows were brought in to help balance the treatment of the water, and while birds feast on the little fish, they breed faster than even the hungriest herons can consume them.

The plant's natural treatment process is not without precedent, according to Rick Volk, chief operator of the wastewater plant.

"The idea of lagoon treatment is as old as Egypt," Volk said. "What we did in Batavia is take a system that is as old as Egypt and apply new technology."

From 2.5 to 3.5 million gallons of raw sewage arrives at the plant daily (capacity is 5 million gallons per day). It is pumped into a screening process that removes everything larger than a cigarette butt, then goes through an aerated grit chamber to remove sand and dirt (this is the one part of the plant that produces any real stench).

After screening, the effluent is pumped into aerated ponds. The ponds provide oxygen treatment that consumes matter in the wastewater. Air is pumped into the water by 200 horsepower compressors. This process takes about a month.

The aerated ponds are popular with ducks who can be found by the dozens either in the water or resting on the long, black aeration pipes that float on the surface of the water.

The wastewater is then fed alum to assist in phosphorus removal as it flows into two secondary ponds. The 45-acre ponds are up to 8-feet deep where biological activity and settling removes more waste. The process takes up to 42 days.

Next, a lift station hoists the water up above the four tertiary ponds, which are from 25 to 35 acres each and have an adjustable depth of 3 to 12 feet. At this point, most of the suspended solids are removed.

This is where you'll find minnows and the waterfowl who feed on them, as well as a variety of other birds flitting through the air, from northern flickers to least flycatchers.

The final step on a molecule of water's journey is to pass through one of three wetlands -- ponds with reeds and other aquatic plants that help "put the final polish," as Volk said, on the wastewater.

The largest of the ponds is popular with ducks, geese, herons and snowy egrets.

The whole process is designed to ensure that only water that is safe for people, crops, fowl and fish is piped back into the Tonawanda.

Plant staff conduct frequent tests -- regulated by the state -- in a lab at the facility to ensure each step of the process is cleaning the waste as it should and that the final product shipped out to the Tonawanda is up to environmental standards.

Staff is on duty from 7 a.m. to 3 p.m., which is the only time the ponds are accessible to the public.

The current four staff members are about half of what the city needed to run its pre-1990s wastewater plant, according to Volk.

While not officially a park, as long as the plant is open, area residents are welcome to visit anytime during plant hours, Volk said.  

Guests are asked to sign a registry in the main building, but are then free to wander the property. With permission, guests can drive their cars -- it can be a long, long walk to the tertiary ponds -- on the well-maintained gravel roads that surround the ponds.

Volk said there are times when work being performed by staff will prevent guests from driving on the roads, which is why it is necessary to ask first.

And if you go, you really want to get back to either the tertiary ponds or the larger of the three wetlands. This is where you will see the greatest variety of birds.

There's also a park of sorts on the west end of the facility, along Donahue Road. There's a small parking lot and footpaths that allow, at points, for visitors to view the tertiary ponds as well as a reconstructed wetland -- abatement for a wetland destroyed when the plant was built. The area is open to the public at all times, but no hunting or trapping is allowed.

More reading: The Wiki Guide to Birds.

If you have trouble viewing the slide show below, click here.

Authentically Local