Batavia’s Board of Education approves increased elevator repair costs during this week’s meeting
Costs are going up with unexpected elevator repairs at Batavia Middle School, as city Board of Education members voted Thursday to approve a transfer of $212,000 from the repair reserve fund.
Business Administrator Scott Rozanski had reviewed the issues and scope of work at the Sept. 19 board meeting, with the vote to occur this month. Members unanimously and without discussion agreed to the transfer for what Rozanski deemed “the worst-case scenario.”
The elevator stopped working in March. Board members had approved an initial transfer of $65,000 for anticipated repairs by Otis Elevator Company in May, Rozanski said. A hydraulic cylinder had ceased to operate and work was to begin then, he said, but supply chain issues delayed it for a while. Work eventually began to repair the cylinder, however, there was an obstruction that prevented anything to continue.
Otis Elevator proposed three phases to be used as needed: Phase I would involve cleaning out the hole, removing the pipe, and continuing the necessary work. If the cylinder casing is good, the issue should be resolved, Rozanski said, and the repair could be completed. The price tag for this first phase would be $35,000.
If it is determined that the casing is bad, then they will move on to Phase II for a new casing and another $26,000. Phase III is the “worst-case scenario” of the first two solutions failing, he said. Work will expand to include redrilling the hole, removing all of the debris, and putting in a hoisting beam, all for an extra $86,000 on top of the other two-phase costs. All totaled, it would be an additional $147,495.
The board’s vote on Thursday changed the original transfer from $65,000 to $212,000 to cover all three options if necessary, Rozanski said. That would leave an available balance of $86,703 in the repair reserve, he said.
At that September meeting, Interim Superintendent Scott Bischoping added that the district’s construction manager obtained second opinions on the recommended work and didn’t just go with Otis Elevator’s proposal.
“This isn’t just a one-company idea,” he said.
The board also approved Campus Construction Management’s proposed cost of $3,875 to conduct a feasibility study on the potential renovation expenses of Batavia Middle School.
In other matters, School board members received some good news during the district’s annual audit Thursday. Christian Townes of Freed Maxick CPAs said the firm issued an “unmodified opinion” for the school district.
“Which is the highest level of assurance that we can provide,” she said.
The overall rating, having no significant deficiencies and having no material misstatements is “a testament” to the hard work the district invests into its financial-related statements, she said.
“Financially, the district is in good shape,” she said. “Overall, you had a really great audit this year. It went smoothly and there are no negative matters to report to you.”
The board voted to accept and approve the final audited report, basic financial statements, and audited extra classroom activity financial statements ending June 30, 2021.